Real judgements, distilled

Legal Case Shots

Court judgements broken down into the case type, how the decision played out, and the lesson worth remembering, with the full judgement available as a PDF.

Frequently asked questions

Is this suitable for use in legal research and court filings?+

Legal Case Shots is built to help you quickly identify and understand relevant precedent. For citation in pleadings or filings, always verify against the full judgment PDF and current citation format (e.g., 2026 INSC ___).

How is a "lesson learnt" different from the judgment's holding?+

The holding is what the court legally decided. The lesson learnt translates that into a practical takeaway: what a lawyer should factor into case strategy or client advice as a result of this precedent.

Is the full judgment available, or just a summary?+

Both. Each case shows a distilled summary (case type, key holding, and lesson learnt) and links to the full judgment as a PDF for when you need the complete text for research or citation.

Can I filter judgments by date or case type?+

Yes. Use Advanced Filters to narrow results by decision date and by practice area, including Constitutional Law, Criminal Law, Service & Administrative Law, Family Law, Civil Property & Inheritance, and Labour & Industrial Law.

Can I search judgments by a specific judge?+

Yes. You can filter judgments by the judge or bench that decided the case, which is useful for tracking how a particular judge has reasoned on similar issues across multiple rulings.

What is Legal Case Shots?+

Legal Case Shots is a searchable database of Supreme Court of India judgments, each broken down into the case type, the court's key holding, and a practical lesson learnt, with the full judgment available as a PDF for citation or deeper reading.

Civil Property & InheritanceSupreme Court of India

Susme Builders Pvt. Ltd. v. Chief Executive Officer, Slum Rehabilitation Authority & Ors.

Civil Appeal · 2018 INSC 1Decided 4 Jan 2018
Civil Appeal No. 18121 of 2017
Justice Madan B. Lokur · Justice Deepak Gupta

Background

Over 800 slum dwellers in Santacruz, Mumbai, who had themselves become owners of the land through a cooperative society, appointed Susme Builders in 1986 to redevelop the slum and rehouse them, but more than three decades later the project remained largely unbuilt despite multiple revised agreements. The Slum Rehabilitation Authority (SRA) eventually cancelled Susme's appointment as developer for delay, and a rival developer, J.G. Developers, also entered the picture claiming consent of the slum dwellers. The Supreme Court had earlier directed a retired judge, Justice B.N. Srikrishna, to determine which developer actually had the mandatory 70% consent of slum dwellers, and this appeal by Susme challenged the SRA's cancellation of its rights and the findings against it.

Decision Breakdown

The Court held that neither Susme nor J.G. Developers had established the requisite 70% consent of slum dwellers needed to run the rehabilitation scheme: Susme because of this failure and its own responsibility for decades of delay, and J.G. Developers because it had obtained consent through a false promise of a larger flat, making its agreements with slum dwellers legally unconscionable and unenforceable. While the Court set aside one narrow part of the Bombay High Court's reasoning (that Susme had been given fair notice on the 70% consent issue specifically), it upheld the SRA's cancellation of Susme's development rights on the independently sufficient ground of delay, and held that Susme was not entitled to any relief. Since both rival developers were disqualified and the slum dwellers' decades-long ordeal could not be allowed to continue, the Court invoked its Article 142 power to do complete justice and issued detailed directions for a fresh, transparent tender process: the SRA was to invite proposals from reputed developers within three weeks, evaluate them on terms no worse than Susme's last offer, require a Rs. 200 crore bank guarantee from the successful bidder, and complete rehabilitation within two years of plan sanction, with the matter to be monitored through further status reports.

Lesson Learnt

A developer appointed to carry out a slum rehabilitation scheme can permanently lose its rights if it fails to prove the legally required level of resident consent and is responsible for prolonged delay, and courts can use their constitutional power to do complete justice to order a fresh, closely supervised process rather than leave vulnerable residents without a remedy.

Susme Builders Pvt. Ltd. v. Chief Executive Officer, Slum Rehabilitation Authority & Ors. – Legal Case Shots | LegalAware