Real judgements, distilled

Legal Case Shots

Court judgements broken down into the case type, how the decision played out, and the lesson worth remembering, with the full judgement available as a PDF.

Frequently asked questions

Is this suitable for use in legal research and court filings?+

Legal Case Shots is built to help you quickly identify and understand relevant precedent. For citation in pleadings or filings, always verify against the full judgment PDF and current citation format (e.g., 2026 INSC ___).

How is a "lesson learnt" different from the judgment's holding?+

The holding is what the court legally decided. The lesson learnt translates that into a practical takeaway: what a lawyer should factor into case strategy or client advice as a result of this precedent.

Is the full judgment available, or just a summary?+

Both. Each case shows a distilled summary (case type, key holding, and lesson learnt) and links to the full judgment as a PDF for when you need the complete text for research or citation.

Can I filter judgments by date or case type?+

Yes. Use Advanced Filters to narrow results by decision date and by practice area, including Constitutional Law, Criminal Law, Service & Administrative Law, Family Law, Civil Property & Inheritance, and Labour & Industrial Law.

Can I search judgments by a specific judge?+

Yes. You can filter judgments by the judge or bench that decided the case, which is useful for tracking how a particular judge has reasoned on similar issues across multiple rulings.

What is Legal Case Shots?+

Legal Case Shots is a searchable database of Supreme Court of India judgments, each broken down into the case type, the court's key holding, and a practical lesson learnt, with the full judgment available as a PDF for citation or deeper reading.

Civil Property & InheritanceSupreme Court of India

The Executive Engineer, Nimna Dudhna Project v. The State of Maharashtra & Others

Civil Appeal · 2020 INSC 45Decided 15 Jan 2020
Civil Appeal Nos. 246-255 of 2020
Justice Ashok Bhushan · Justice M.R. Shah

Background

Land was acquired for an irrigation project in Maharashtra, and a batch of landowners' first appeals (filed five and a half years late) were allowed by the High Court, which enhanced their compensation to match what other landowners for the same project had already received, and also awarded statutory benefits and interest for the entire period, including the years of delay. The government body that acquired the land (the Executive Engineer) appealed, not disputing the compensation increase itself, but objecting specifically to being made to pay interest for the period that the claimants themselves had delayed in approaching the court.

Decision Breakdown

The Supreme Court partly allowed the appeals. It agreed that the compensation amount itself, and the condoning of the delay in filing the appeals, were correctly decided and could not be reopened. However, relying on its own earlier precedents, it held that a public body should not be saddled with paying interest for a period of delay that was not its fault: if claimants take years to come to court, they cannot also claim interest on the extra compensation for that same delayed period. The High Court's order was modified only to remove the interest for the delay period, while the rest of the compensation award was left undisturbed.

Lesson Learnt

If you delay challenging a compensation order for years before going to court, you may still eventually win a higher compensation amount, but you generally cannot also claim interest on that increase for the years you yourself took to act.

The Executive Engineer, Nimna Dudhna Project v. The State of Maharashtra & Others – Legal Case Shots | LegalAware