Adavya Projects Pvt. Ltd. v. M/S Vishal Structurals Pvt. Ltd. & Ors.

Civil Appeal · 2025 INSC 507Decided 17 Apr 2025
Civil Appeal No. 5297 of 2025 (arising out of SLP (C) No. 25746 of 2024)
Justice Pamidighantam Sri Narasimha

Background

The appellant and respondent no. 1 formed a limited liability partnership (respondent no. 2) to execute oil-and-gas projects, with respondent no. 3 designated as the LLP's CEO under the partnership agreement, which contained an arbitration clause. A dispute arose over reconciliation of project accounts, and the appellant sent an arbitration notice and filed a court application for appointment of an arbitrator, but named only respondent no. 1, not the LLP or its CEO. After the arbitrator was appointed, the appellant tried to also bring in the LLP and its CEO as parties to the arbitration claim. The arbitral tribunal, and later the High Court, ruled this could not be done because those two had never been served the arbitration notice or named in the court application, so the appellant appealed to the Supreme Court.

Decision Breakdown

The Supreme Court held that a notice invoking arbitration and the list of parties named in the court application for appointing an arbitrator are not final limits on who can later be made a party to the arbitration. The court's role at the appointment stage is only a limited, preliminary screening, not a final decision on scope or parties. The real question, the Court held, is whether the person sought to be added actually consented to be bound by the arbitration agreement, applying the "Group of Companies" test from Cox and Kings v. SAP India, looking at mutual intent, the relationship between signatory and non-signatory, commonality of subject matter, and how the non-signatory actually performed the contract. Applying this, the Court found that the LLP was created by and operated entirely under the partnership agreement, and its CEO acted throughout under his contractual role defined in that agreement, so both had, through their conduct, effectively agreed to be bound by its arbitration clause even without signing it separately. The Court allowed the appeal, set aside the High Court's order, and directed that both be added as parties before the arbitral tribunal, with proceedings to continue from where they had been halted.

Lesson Learnt

Not sending a formal arbitration notice to someone, or leaving them out of the initial court application to appoint an arbitrator, does not permanently protect them from being added to the arbitration later. If their own conduct shows they operated under the same contract and consented to its terms, they can still be pulled into the arbitration as a party.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case