Alka Chandewar v. Shamshul Ishrar Khan

Civil Appeal · 2017 INSC 593Decided 6 Jul 2017
Civil Appeal No. 8720 of 2017
Justice Rohinton Fali Nariman · Justice Sanjay Kishan Kaul

Background

A sole arbitrator had passed an interim order restraining the respondent from disposing of certain flats without the tribunal's leave, but the respondent allegedly transferred five flats in breach of that order. The arbitrator found the breach proved and referred the matter to the Bombay High Court as a representation for contempt under Section 27(5) of the Arbitration and Conciliation Act, 1996. The Bombay High Court read Section 27(5) narrowly, holding it applied only to contempt relating to assistance in taking evidence, not to breach of other interim orders, and dismissed the contempt reference as not maintainable and time-barred.

Decision Breakdown

The Supreme Court held that the Bombay High Court's restrictive reading of Section 27(5) was wrong: the provision was intended to give real teeth to an arbitral tribunal's orders by allowing the tribunal to make a representation to the Court for contempt of any default or misconduct during the proceedings, not merely non-cooperation in evidence-taking. The Court also noted that a subsequent 2015 amendment inserting Section 17(2), which makes an arbitral tribunal's interim orders directly enforceable as if they were court orders, was enacted precisely to fill this gap, confirming the broader legislative intent rather than undermining the appellant's reading. It therefore allowed the appeal, set aside the Bombay High Court's judgment on the legal question of maintainability, and remanded the case to the High Court to decide, on the facts, whether the respondent had actually committed contempt, leaving it open to the respondent to argue on remand that no contempt occurred.

Lesson Learnt

A party who disobeys an arbitral tribunal's interim order (such as a freeze on disposing of property) can be proceeded against for contempt under the Arbitration Act: the remedy is not limited to non-cooperation with evidence-taking, and courts must give real enforcement teeth to arbitral interim orders rather than reading the law narrowly to defeat them.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case