Anglo American Metallurgical Coal Pty Ltd. v. MMTC Ltd.

Civil Appeal · 2020 INSC 705Decided 17 Dec 2020
Civil Appeal No. 4083 of 2020
Justice Rohinton Fali Nariman · Justice K.M. Joseph

Background

An Australian coal supplier and the Indian public sector company MMTC Ltd. were parties to a long-term coal supply agreement. A dispute arose over MMTC's failure to lift the contracted quantity of coal during the "Fifth Delivery Period" (2008-09), with the supplier claiming damages for breach. An international arbitral tribunal of three arbitrators issued a majority award (2 of 3) in favour of the supplier, with one arbitrator dissenting. A single judge of the Delhi High Court upheld the majority award under Section 34 of the Arbitration Act, but a Division Bench of the same High Court later reversed this and set aside the award under Section 37 (an appeal from a Section 34 order). The coal supplier then appealed to the Supreme Court.

Decision Breakdown

The Supreme Court restored the arbitral tribunal's majority award, holding that the Delhi High Court's Division Bench had exceeded the very limited scope of judicial review permitted under Sections 34 and 37 of the Arbitration Act. Reaffirming its earlier landmark ruling in Associate Builders v. DDA and later cases, the Court explained that a court cannot sit in appeal over an arbitral award or substitute its own view of the facts or contract interpretation for that of the arbitrators: interference is permitted only if the award is "patently illegal," conflicts with the fundamental policy of Indian law, or is so perverse that no reasonable person could have reached that conclusion based on the evidence. Since the majority award here represented one possible, reasonable reading of the correspondence and conduct between the parties, it could not be labelled perverse merely because an alternative interpretation existed. The Court therefore set aside the Division Bench's judgment and restored both the arbitral award and the Single Judge's earlier ruling upholding it.

Lesson Learnt

When parties choose arbitration to resolve a commercial dispute, courts will generally respect the arbitrator's decision and intervene only in narrow circumstances, such as fraud, a decision no reasonable person could have reached, or a clear violation of law, and not simply because a court might have read the contract differently.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case