Bharat Broadband Network Limited v. United Telecoms Limited

Civil Appeal · 2019 INSC 537Decided 16 Apr 2019
Civil Appeal No. 3972 of 2019
Justice Rohinton Fali Nariman · Justice Vineet Saran

Background

Bharat Broadband Network Limited (BBNL) awarded a tender for a telecom infrastructure project to United Telecoms Limited, under a contract whose arbitration clause named BBNL's own Chairman-cum-Managing Director (CMD) as the sole arbitrator. A dispute arose and was referred to a person appointed under that clause, but Parliament's 2015 amendment to the Arbitration Act added Section 12(5), disqualifying certain persons with a connection to a party from acting as arbitrators unless both sides expressly waived the objection in writing after the dispute arose. BBNL applied to terminate the arbitrator's mandate on this ground, but the High Court held BBNL had effectively waived the objection by participating in the arbitration, including through an appointment letter.

Decision Breakdown

The Supreme Court held that Section 12(5)'s bar is mandatory and can only be waived by an "express agreement in writing" made after the dispute has arisen: mere conduct, such as issuing an appointment letter or the other party filing a statement of claim, cannot amount to such a waiver. Since no such express written waiver existed here, the arbitrator (who fell within the categories of persons ineligible under the Seventh Schedule to the Act) became "de jure unable to perform his function," and his mandate stood automatically terminated by operation of law. The Court allowed the appeal, set aside the High Court's judgment, and directed that a substitute arbitrator be appointed with the consent of both parties; since arbitral proceedings had continued in the interim and resulted in two awards, those awards were also set aside as a consequence, rendering related Section 34 challenge proceedings infructuous.

Lesson Learnt

When a contract's arbitration clause nominates an arbitrator connected to one of the parties, that appointment is void unless both sides give an actual written waiver after the dispute arises: simply continuing to participate in arbitration proceedings is not enough to cure this defect, and any awards rendered by an ineligible arbitrator can be set aside even after the fact.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case