Bhupesh Bhayana and Another v. Kunal Seth and Another

Civil Appeal · 2026 INSC 546Decided 26 May 2026
C.A. No.-008192-008193 - 2026
Justice Sanjay Kumar · Justice K. Vinod Chandran

Background

In 2010, the owners of an old building (the Bhayana family) and a builder (the Seth family) agreed that the builder would reconstruct the building in exchange for retaining a floor and paying compensation, with penalty clauses for delay (Clause 7) and for outright breach (Clause 13). The builder abandoned construction in 2011 after completing only part of the structure, prompting arbitration. The arbitrator awarded the owners a delay penalty under Clause 7 but denied them the separate breach-based forfeiture under Clause 13, and also awarded the builder refund of his deposit plus construction costs. A Delhi High Court judge modified the penalty period, and a Division Bench, on further appeal, denied the owners any penalty at all for want of proof of actual damage, leading to this appeal before the Supreme Court.

Decision Breakdown

The Supreme Court held that the Division Bench erred in denying the owners compensation for the builder's delay merely because they had not separately proved actual damage: the agreement's day-to-day penalty clause itself built in the presumption of loss. It also found the arbitrator's award "patently illegal" for treating Clauses 7 and 13 as mutually exclusive instead of applying both, and for miscalculating the penalty period, but noted the owners never challenged this illegality within the Section 34 limitation period, so it had attained finality on that specific point. Rather than setting aside the award and forcing the parties into a fresh decade-plus round of litigation, the Court invoked its power under Article 142 of the Constitution to do complete justice, recalculating the amounts due and fixing a final net balance payable by the owners to the builder's family, with no interest payable to either side.

Lesson Learnt

Courts can use their extraordinary constitutional power (Article 142) to finally settle long-running arbitration disputes with a fair recalculation rather than sending parties back to square one, but a party who does not timely challenge an error in an arbitral award within the statutory limitation period risks losing the right to correct even a genuinely illegal part of that award.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case