Bhushan Power & Steel Ltd. v. Rajesh Verma
Background
Bhushan Power & Steel had obtained a final Supreme Court direction requiring Odisha to recommend iron-ore reserves for its steel plant under the State's commitments. The State acted concerning one mining area but did not send the recommendation concerning Keora. It cited overlapping applications, other litigation and statutory requirements, while three other companies sought similar relief directly in the Supreme Court.
Decision Breakdown
The Court held the State officials in contempt for failing to comply with the final Keora direction. They could not reopen rights already decided between these parties by raising legal or competing-application arguments at the implementation stage. They received one final month from receipt of the order to transmit the recommendation, which would discharge the contempt; the Central Government remained free to decide its merits according to law. Third-party intervention applications in the contempt proceedings were rejected. The three companies' Article 32 petitions were dismissed with liberty to approach the High Court or another available forum, leaving their merits open because non-grant of a mining lease did not establish a fundamental-right violation.
Lesson Learnt
An authority must implement a final court direction rather than relitigate objections while resisting compliance. Here the enforceable duty was to send a recommendation, and neither that direction nor the contempt finding guaranteed the Central Government would grant the mining lease.