Bikram Chatterji & Ors. v. Union of India & Ors.
Background
This is an interim order, not a final judgment. In its 23.07.2019 judgment in the Amrapali homebuyers' case, the Court decided the main prayers and kept supervising the completion of the projects. Several applications were filed during that phase.
Decision Breakdown
This is an interim order, not a final judgment. The Court protected NBCC from being made a party to homebuyers' cases elsewhere, changed an interest repayment schedule for Royalgolf Link City Projects, dealt with bank financing for homebuyers and fixed a reduced interest rate on dues owed to the Noida and Greater Noida authorities.
Lesson Learnt
There is no final ruling in these applications on the wider case. The Court continues to supervise the completion of Amrapali's projects.