Chandigarh Housing Board v. M/s. Parasvanath Developers Pvt. Ltd. & Anr.

Civil Appeal · 2019 INSC 1392Decided 17 Dec 2019
Civil Appeal No. 10748 of 2016
Justice Mohan M. Shantanagoudar · Justice R. Subhash Reddy

Background

Chandigarh Housing Board (CHB) partnered with a private developer to build a residential project, and a buyer paid over Rs. 1 crore towards a flat under a tripartite agreement. When construction never started due to a land-encumbrance dispute between CHB and the developer, the buyer sought a refund and approached the National Consumer Disputes Redressal Commission, which ordered CHB and the developer to jointly refund the principal with 10% interest, plus Rs. 1 lakh each for mental harassment and litigation costs, split 70:30 between the developer and CHB. CHB appealed to the Supreme Court, disputing only its 30% share of the harassment/litigation costs and the enhanced interest rate, arguing a specific contractual compensation clause should make the developer solely liable.

Decision Breakdown

The Supreme Court held that the contractual compensation clause (Clause 9(c), a fixed per-square-metre penalty for late possession) did not apply here because construction never even began, so the clause's trigger condition was never met; the Rs. 1 lakh awards for mental harassment and litigation costs were general lump-sum amounts, not the specific compensation contemplated by that clause. It held that a prior arbitration award (binding as between CHB and the developer) which attributed the project's failure to breaches by both parties, apportioning liability 70:30, had attained finality and matched how the two had already split the sale proceeds under an escrow agreement, so that same ratio properly governed the consumer liability too. It also upheld the Commission's discretionary increase of the interest rate from 9% to 10% as unobjectionable. The appeal was dismissed, with CHB directed to pay its remaining 30% share of costs plus an extra 1% interest on its portion within eight weeks.

Lesson Learnt

A contract clause fixing compensation for a specific type of breach (like late delivery) does not automatically cover every liability arising from the deal: general damages like litigation costs or harassment compensation can still be split according to a separately established liability ratio (here, from an arbitration award), even between joint obligors.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case