DC Multi Modal Park Pvt Ltd vs. Maharashtra MMLP Pvt. Ltd. & Anr.

Original Miscellaneous Petition (Interim, Commercial) · 2026:DHC:7350Decided 1 Sept 2026New Delhi Bench
O.M.P.(I) (COMM.) 145/2026CNR: DLHC010133722026
Justice Tushar Rao Gedela

Background

DC Multi Modal Park was the "Concessionaire" under a Concession Agreement (12.12.2023) to build and operate a Multi Modal Logistics Park at Nagpur for Maharashtra MMLP Pvt. Ltd. ("the Authority"). When Phase I fell behind schedule, the Authority terminated the agreement in September 2025. The petitioner's first bid for court-ordered interim relief was rejected in December 2025, with the parties told to go to arbitration. While arbitration was being set up, the Authority re-tendered the balance work and awarded it to a new bidder (respondent no. 2) in March 2026. The petitioner then filed this second petition to block the new contract and get reinstated.

Decision Breakdown

The Court held this second Section 9 petition was barred because it sought essentially the same reliefs as the first petition, which had already been refused: a party cannot keep re-litigating an identical prayer for interim relief. On the facts, the Court also found the petitioner had known about the re-tendering for months without objecting, and only rushed to court once the new contract was about to be signed, undermining its case for urgent relief. The Court further relied on Sections 20A and 41(ha) of the Specific Relief Act, 1963, which discourage courts from injuncting infrastructure projects, and read the contract's own "continuity upon termination" clause as allowing the Authority to get the work done by someone else, leaving the ousted concessionaire to damages or reinstatement only if termination is later set aside. The petition was dismissed with Rs. 1 lakh costs, and the interim status-quo order was vacated. The Court also criticized the petitioner for not properly serving the new bidder with the case papers in advance.

Lesson Learnt

Courts are reluctant to grant a second, near-identical application for interim relief once similar relief has already been refused, and are especially cautious about injuncting infrastructure projects: delay in approaching the court, and procedural shortcuts like skipping advance service on an affected party, can be fatal to a claim for urgent relief.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case