Dharambeer Kumar Singh vs. The State of Jharkhand & Anr.

Not available · 2024 INSC 583Decided 6 Aug 2024
Not available
Justice Vikram Nath · Justice Prasanna B. Varale

Background

The appellant, who had worked as a sub-contractor, filed a complaint alleging that a contracting firm and its partners obtained a government irrigation-project tender worth over Rs. 35 crore by submitting forged and fabricated experience certificates, and separately that money owed to him as sub-contractor went unpaid. After two investigations initially found insufficient evidence, the trial Magistrate rejected both closure reports, found the certificates were indeed fabricated, and issued a summoning order for trial. The accused then got the Jharkhand High Court to quash the summoning order and the entire criminal proceeding under its inherent powers (Section 482 CrPC), holding that it was actually the complainant, not the accused, who had manipulated the documents.

Decision Breakdown

The Supreme Court held that the High Court had overstepped its limited jurisdiction under Section 482 CrPC by effectively conducting a "mini-trial" and returning a finding on who forged the documents: an appreciation-of-evidence exercise that can only properly happen during an actual trial, not at the summons stage. Citing CBI v. Aryan Singh, the Court reiterated that at the quashing/discharge stage, a court's only job is to check whether sufficient material exists to proceed against the accused, not to weigh competing evidence. Even accepting that the complainant may have played some role in altering the certificate, the accused firm's partner was still the undisputed ultimate beneficiary of the fraudulently obtained tender, and "two wrongs do not make a right": his potential complicity could not be resolved by prematurely quashing the case. The Court therefore set aside the High Court's quashing order and restored the criminal proceedings, sending the matter back to the Magistrate for a full trial, while leaving all defences open to the accused.

Lesson Learnt

A High Court exercising its inherent power to quash a criminal case cannot conduct a mini-trial or decide disputed factual questions (like who actually forged a document); it may only check whether there is enough material to justify a trial: genuine disputes about guilt must be resolved by the trial court itself, not short-circuited at the quashing stage.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case