DLF Home Developers Limited v. Rajapura Homes Private Limited
Background
DLF Home Developers Limited (DHDL) had sold its stake in two real-estate special purpose vehicles and, as part of the deal, separately agreed to complete construction obligations under two "Construction Management Agreements." When DHDL certified that construction was complete, the companies refused to accept the certification and also disputed whether a payment of Rs. 75 crore was owed. DHDL sought to refer the dispute to arbitration under the Construction Management Agreements, but the other side argued the real dispute actually fell under a different, earlier set of agreements (Share Purchase Agreements) that required arbitration in Singapore instead of India. DHDL approached the Supreme Court under Section 11(6) of the Arbitration Act to get a sole arbitrator appointed.
Decision Breakdown
The Supreme Court held that at the Section 11 stage, its role is narrowly limited to checking whether a valid, written arbitration agreement exists and whether there is at least a prima facie arbitrable dispute: it should not conduct a detailed inquiry into which of two overlapping agreements truly governs the dispute. Finding that the Construction Management Agreements contained valid, independent arbitration clauses and that the dispute (over fees for completed construction) was genuinely connected to those agreements, the Court held the matter was arbitrable under them rather than exclusively under the Share Purchase Agreements. It appointed a retired Supreme Court judge as the sole arbitrator for both related petitions, while leaving it to the arbitrator to decide if the proceedings should be consolidated, and clarified that if the arbitrator later finds the "real dispute" actually stems from the Share Purchase Agreements, the parties remain free to pursue arbitration under those agreements instead.
Lesson Learnt
When a commercial relationship is governed by multiple linked contracts with different arbitration clauses, a court deciding only whether to appoint an arbitrator will not try to conclusively settle which contract governs: it will refer the matter to arbitration if a plausible case exists, leaving the deeper question of jurisdiction to the arbitrator himself.