DLF Ltd. (formerly known as DLF Universal Ltd.) and Anr. vs. Koncar Generators and Motors Ltd.

Not available · 2024 INSC 593Decided 8 Aug 2024
Not available
Justice Pamidighantam Sri Narasimha · Justice Aravind Kumar

Background

DLF Ltd. and a Croatian company, Koncar Generators and Motors Ltd., had a contract for design and supply of generators that went to international arbitration in Paris, resulting in a 2004 award of roughly Euros 10.9 lakh plus interest in Koncar's favour. While DLF's objections to the award were pending in Indian courts, DLF deposited amounts (Rs. 7.5 crore in 2010 and Rs. 50 lakh in 2011) with the court, and a dispute arose over which date's euro-to-rupee exchange rate should be used to convert the foreign-currency award into Indian rupees for enforcement.

Decision Breakdown

The Supreme Court held that under the Arbitration and Conciliation Act, 1996, a foreign award becomes enforceable, and its currency should be converted, on the date the objections against it are finally decided, following the principle in Forasol v. ONGC. However, where the award-debtor deposits money in court during the pendency of objections and the award-holder is permitted to withdraw it, that deposited portion must instead be converted at the exchange rate prevailing on the date of deposit (per Renusagar Power Co. v. General Electric), since the award-holder could have accessed and benefited from it then. Applying this, the Court held the first deposit (Rs. 7.5 crore, withdrawable in 2010) converts at the 2010 rate, while the second deposit (not withdrawable until proceedings concluded) and the remaining award amount convert at the rate prevailing when the objections finally attained finality in 2014.

Lesson Learnt

When a foreign-currency arbitral award is being enforced in India, the exchange rate used to convert it into rupees is not fixed at a single point: money the paying party actually makes available for withdrawal is converted at that deposit date, while any remaining award amount is converted only once the legal challenges to the award are finally resolved.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case