Executive Engineer (R and B) and Others vs Gokul Chandra Kanungo (Dead) through his LRs.

Civil Appeal · 2022 INSC 1043Decided 30 Sept 2022
Civil Appeal No. 8990 of 2017
B.R. Gavai · B.V. Nagarathna

Background

The respondent contractor was awarded a road construction contract in 1971, which was completed years late in 1977. After remaining silent for about 12 years, he issued a claim notice in 1989 and eventually filed a suit seeking reference to arbitration; further delays (about 10 more years) followed before an arbitrator was finally appointed in 2001. In 2004, the arbitrator awarded about Rs. 9.2 lakh on the merits of the claim, but also awarded interest at 18% per annum for the entire period since 1976 (including the years of the contractor's own inaction), amounting to nearly five times the principal award. The District Court and the Orissa High Court both upheld the award, prompting this appeal by the government engineering department.

Decision Breakdown

The Supreme Court held that under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, an arbitrator has discretion to award interest at a rate it "deems reasonable," but must exercise that discretion with application of mind, considering the parties' conduct and the facts of the case, which the arbitrator here failed to do. The Court found the contractor's own prolonged inaction (roughly 12 years of silence after project completion, and roughly 10 more years of delay before the arbitrator was appointed) disentitled him to interest for those specific periods, since a party cannot benefit from its own lapses. Exercising its power under Article 142 of the Constitution and relying on precedents (Rajendra Construction Co., Krishna Bhagya Jala Nigam, and McDermott International), the Court left the principal award of about Rs. 9.2 lakh undisturbed but reduced the interest rate for all remaining periods (pre-reference, pendente lite, and post-award) from 18% to 9% per annum, and excluded interest altogether for the periods of the contractor's own delay.

Lesson Learnt

An arbitrator's discretion to award interest is not unlimited. It must be exercised with reasons tied to the facts, and a claimant who delays pursuing his own claim for years cannot expect interest to run for those periods of his own inaction; courts (including the Supreme Court under Article 142) can and do moderate exorbitant interest awards to serve the interests of justice.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case