Flemingo (DFS) Private Limited vs. Airports Authority of India

Arbitration Petition · 2026:DHC:7608Decided 7 Sept 2026New Delhi Bench
ARB.P. 853/2025CNR: DLHC010360382025
Justice Jasmeet Singh

Background

A duty-free shop operator at Amritsar Airport had a long-running dispute with the Airports Authority of India (AAI) over alleged excess rent, royalty, and concession fees charged under a 2011 licence agreement. The operator sent several letters from 2017 requesting resolution, but AAI only formally rejected the claims in 2021. After failed attempts at mediation through 2023, the operator sought court-appointed arbitration in 2025. AAI opposed the petition, arguing it was filed too late and that some claims fell outside the arbitration clause altogether.

Decision Breakdown

The Court held that at this preliminary stage, its job is only to check that a valid arbitration agreement exists and that the petition itself was filed within the legal time limit, not to decide whether the underlying claims are themselves too old, which is for the arbitrator to determine. The Court found the early letters (2017-2018) were not true "notices invoking arbitration" since they merely requested a resolution and warned of arbitration only as a future possibility; the real "breaking point" for limitation purposes was when AAI actually rejected the claims in October 2021. Since a formal notice invoking arbitration followed in March 2022, and the subsequent months spent in genuine mediation (encouraged by AAI's own policy) are excluded from the limitation clock, the petition was filed in time. An arbitrator was appointed, leaving all merits, including whether one of the disputed items falls within the arbitration clause, to be decided in arbitration.

Lesson Learnt

A letter merely requesting resolution and warning that arbitration "may" follow is not the same as formally invoking arbitration; and time spent in good-faith settlement talks or mediation, especially where the other party itself proposed it, is excluded when calculating whether a court arbitration petition was filed within the legal time limit.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case