Gayatri Balasamy v. M/s ISG Novasoft Technologies Limited

Civil Appeal · 2025 INSC 605Decided 30 Apr 2025
C.A. Nos.-006178-006179 - 2025 (arising out of S.L.P.(C) Nos. 15336-15337 of 2021, along with a batch of connected appeals)

Background

This case arose from a dispute between Gayatri Balasamy and her former employer, ISG Novasoft Technologies, that had gone to arbitration and produced an award later challenged in court. Because previous Supreme Court benches had given conflicting answers on a recurring and important question, whether a court reviewing an arbitral award under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996 can modify the award, or can only set it aside: a three-judge bench referred the question to the Chief Justice, who in turn constituted this five-judge Constitution Bench to settle the law once and for all.

Decision Breakdown

By a 4:1 majority, the Court held that Sections 34 and 37 courts do have a limited power to modify an arbitral award, though not a general appellate power to review it on its merits. This limited power applies in four situations: (i) severing and setting aside only the "invalid" portion of an award where it is separable from the valid part; (ii) correcting clerical, computational, or typographical errors that are obvious on the face of the record; (iii) modifying post-award interest in appropriate circumstances; and (iv) invoking the Supreme Court's special Article 142 "complete justice" power, used sparingly and never to rewrite an award's merits. Justice K.V. Viswanathan dissented, holding that the earlier ruling in Project Director, NHAI v. M. Hakeem (that courts cannot modify awards) was correctly decided, and that only the narrow power to fix clerical or computational errors should be recognised: modification, in his view, is not a "lesser" power contained within the power to set aside, but a fundamentally different one that risks turning courts into appellate bodies over arbitration.

Lesson Learnt

Parties who go to arbitration in India should know that courts reviewing the award can now, in limited and defined situations, tweak or partially fix an award rather than only accepting or scrapping it entirely, but this is a narrow exception, not a licence for courts to re-decide the case on its merits.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case