General Manager East Coast Railway Rail Sadan & Anr. vs Hindustan Construction Co. Ltd.

Civil Appeal · 2022 INSC 743Decided 22 Jul 2022
Civil Appeal No. 4747 of 2022
M.R. Shah · B.V. Nagarathna

Background

A construction contractor and the East Coast Railway had a contract dispute. The contractor first went to a court in Visakhapatnam under Section 9 of the Arbitration and Conciliation Act to seek an interim order stopping the Railway from encashing a bank guarantee. Later, when the contractor wanted an arbitrator appointed after disputing the validity of the arbitral tribunal the Railway had constituted, it filed a fresh application under Section 11(6) of the Act, but this time before the Orissa High Court at Cuttack, not before the Andhra Pradesh High Court connected to Visakhapatnam. The Railway objected that only the Andhra Pradesh High Court had jurisdiction, but the Orissa High Court still went ahead and appointed an arbitrator, reasoning that since the Railway did not oppose having an arbitrator in principle, there was no point sending the contractor elsewhere.

Decision Breakdown

The Supreme Court held that Section 42 of the Arbitration and Conciliation Act is a strict rule: once any application under Part I of the Act (such as the earlier Section 9 application) is made in a particular court, that same court alone has jurisdiction over all subsequent applications relating to the same arbitration agreement, and no other court can entertain them. Since the contractor had already approached the court at Visakhapatnam (within Andhra Pradesh's jurisdiction) first, only the Andhra Pradesh High Court could hear the later Section 11(6) application, not the Orissa High Court. The fact that the Railway did not oppose appointing an arbitrator in principle could not itself create jurisdiction where none existed. The Supreme Court therefore quashed the Orissa High Court's order appointing the arbitrator, but allowed the contractor to file a fresh Section 11(6) application before the Andhra Pradesh High Court within four weeks, directing that it be decided promptly on its merits, with no order as to costs.

Lesson Learnt

Under Section 42 of the Arbitration Act, once a party approaches a particular court for any relief connected to an arbitration agreement, all later arbitration-related applications on that same agreement must go to that same court: parties cannot pick a different, more convenient court later, even if the other side does not strongly object.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case