Giriraj Garg v. Coal India Ltd. & Ors.

Civil Appeal · 2019 INSC 211Decided 15 Feb 2019
Civil Appeal No. 1695 of 2019
Justice Uday Umesh Lalit · Justice Indu Malhotra

Background

Coal India Ltd. ran a 2007 e-Auction Scheme for coal distribution, which contained an arbitration clause (Clause 11.12) covering disputes "arising out of" or "in relation to" the Scheme. The appellant, a coal buyer, had a dispute with a Coal India subsidiary arising from sale orders issued under this Scheme and applied to the Jharkhand High Court under Section 11(6) of the Arbitration Act for appointment of an arbitrator. A Single Judge rejected the application, apparently holding that the arbitration clause in the Scheme did not extend to disputes under the individual sale orders. The buyer appealed to the Supreme Court.

Decision Breakdown

The Supreme Court allowed the appeal and set aside the High Court's order, holding that Clause 11.12 of the 2007 Scheme stood validly incorporated into the sale orders issued under it, making this a "single contract case" where the arbitration clause in a standard-form document (the Scheme) extends to transactions referencing it. Relying on precedents interpreting phrases like "arising out of," "in relation to," and "in connection with" as being of the widest amplitude (Renusagar Power Co. v. General Electric; Doypack Systems v. Union of India), the Court held the clause covered the sale transaction dispute in question. At the parties' joint request, the Court itself appointed a named retired High Court judge as sole arbitrator to decide the dispute, with proceedings to be held in Kolkata.

Lesson Learnt

An arbitration clause written into a master scheme or standard-form document can bind parties to arbitration even for disputes arising under separate transactional documents (like individual sale orders) that merely reference the scheme: courts read phrases like "arising out of" or "in relation to" broadly when deciding whether a dispute falls within an arbitration clause's scope.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case