Glencore International AG v. M/S Shree Ganesh Metals

Civil Appeal · 2025 INSC 1036Decided 25 Aug 2025
Civil Appeal No. 11067 of 2025 (arising from SLP(C) No. 27985 of 2019)
Justice Sanjay Kumar · Justice Satish Chandra Sharma

Background

Glencore International AG, a Swiss commodity trading company, and Shree Ganesh Metals, an Indian zinc-alloy producer, had a history of contracts for zinc metal purchases, each containing a London-seated arbitration clause. In 2016 the parties negotiated a fresh contract for 6,000 metric tons of zinc, exchanged confirming emails, and Glencore sent a signed written contract, but Shree Ganesh never signed it, even though it went on to accept deliveries, raise/honour invoices, and furnish Letters of Credit referencing that very contract. When a dispute arose over Letters of Credit and non-supply of the remaining quantity, Shree Ganesh sued in the Delhi High Court, and Glencore sought reference to arbitration under Section 45 of the Arbitration and Conciliation Act, 1996, both the Single Judge and the Division Bench refused, holding no concluded, binding contract (and hence no arbitration agreement) existed since the contract was unsigned.

Decision Breakdown

The Supreme Court reversed both lower court rulings, holding that an arbitration agreement need not be signed if the record of agreement is otherwise established: through an exchange of emails, invoices, and conduct demonstrating both parties acted upon the contract. Since Shree Ganesh accepted 2,000 metric tons under the contract, referenced its specific contract number in correspondence and Letters of Credit, and never disputed those terms until litigation arose, its conduct amounted to acceptance including the arbitration clause. The Court relied on precedents holding that signature is not a mandatory requirement under Section 7 of the Act where conduct and correspondence show the parties were "ad idem." It set aside the High Court orders and directed that the dispute be referred to arbitration in London as agreed.

Lesson Learnt

In commercial contracts, actions speak louder than signatures. If a party accepts goods, raises invoices, and issues payment instruments under a written but unsigned contract, it cannot later disown the arbitration clause in that same contract by pointing to the missing signature.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case