GR Green Life Energy Pvt. Ltd. v. Leitwind Shriram Manufacturing Pvt. Ltd.

Civil Appeal · 2021 INSC 107Decided 22 Feb 2021
Civil Appeal No. 692 of 2021
Justice Indu Malhotra · Justice Ajay Rastogi

Background

GR Green Life Energy (the contractor/appellant) and Leitwind Shriram Manufacturing had signed a 2014 Development Agreement to set up a wind farm in Maharashtra, containing a three-member arbitration clause. After a payment dispute arose, the respondent invoked arbitration and sought appointment of an arbitrator from the Madras High Court when the appellant did not nominate its own arbitrator; meanwhile, the appellant separately registered under the MSMED Act and sought resolution through the Facilitation Council, Pune. The Madras High Court held that counter-claims could not be referred to the MSMED Facilitation Council and appointed an arbitration process under the 1996 Act, which the appellant then challenged before the Supreme Court.

Decision Breakdown

During the Supreme Court proceedings, both parties agreed to resolve their disputes through a Court-appointed Sole Arbitrator instead of the three-member tribunal originally envisaged in the contract. The Court accordingly appointed a former High Court judge as Sole Arbitrator to decide all claims and counter-claims arising from the Development Agreement, to be conducted by the Madras High Court Arbitration Centre under its rules and the appointee's Section 12 independence/impartiality declarations. As a consequence, the parallel proceeding the appellant had initiated before the MSMED Facilitation Council, Pune was directed to stand closed, and the appeal was disposed of in these agreed terms.

Lesson Learnt

Parties can modify their original arbitration clause by mutual consent even during litigation (here, moving from a three-member panel to a sole arbitrator), and registering under the MSMED Act does not allow a contractor to sidestep a validly invoked arbitration clause when the dispute involves counter-claims the MSMED Act's Facilitation Council has no power to adjudicate.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case