Hampi Expressways Private Limited vs. National Highways Authority of India
Background
In an ongoing arbitration between a highway developer and NHAI, being heard by a tribunal of three former senior judges, both sides jointly told the Court that evidence was still being presented and that more time was needed to complete the case and deliver an award.
Decision Breakdown
Given the parties' joint request and the nature of the matter, the Court extended the time available for the arbitral tribunal to complete proceedings and render its award until 30 September 2027.
Lesson Learnt
India's arbitration law imposes time limits on arbitrators to keep cases moving, but courts will extend these deadlines where both parties agree that more time is genuinely needed for a complex dispute, rather than forcing a premature award.