Hindustan Zinc Limited (H.Z.L.) v. Ajmer Vidyut Vitran Nigam Limited

Civil Appeal · 2019 INSC 1319Decided 4 Dec 2019
Civil Appeal No. 9212 of 2019
Justice Rohinton Fali Nariman · Justice Aniruddha Bose · Justice V. Ramasubramanian

Background

Hindustan Zinc Limited had a captive power plant and used open access arrangements to wheel electricity from that plant to three of its own industrial units, through the distribution system of Ajmer Vidyut Vitran Nigam Limited (AVVNL). A billing dispute arose over "unscheduled interchange" charges under their open access agreements, and the Rajasthan Electricity Regulatory Commission referred the dispute to an arbitrator under Section 86(1)(f) of the Electricity Act, 2003. The arbitrator ruled substantially in Hindustan Zinc's favour, but AVVNL later argued, for the first time before the High Court, in a Section 37 appeal, that the arbitrator had never had jurisdiction in the first place. The Rajasthan High Court agreed and set aside the entire arbitral award.

Decision Breakdown

The Supreme Court upheld the High Court's view that Section 86(1)(f) of the Electricity Act only allows the State Commission to refer disputes between a licensee (the distribution company) and a generating company to arbitration: it does not cover a dispute between a licensee and a mere open-access consumer, which is instead governed by Section 42 of the Act and its own separate three-tier grievance mechanism. Since Hindustan Zinc was using its captive plant's power for its own consumption (as a consumer) rather than acting as a generating company selling power, the dispute fell outside Section 86(1)(f), making the arbitrator's appointment itself without jurisdiction and the resulting award a nullity in law. The Court also held that a jurisdictional defect of this kind can be raised at any stage, even after a party initially consented to arbitration, relying on the settled principle that a decision rendered without jurisdiction is a nullity. However, the Court clarified that the High Court should not have gone on to examine the merits of the award once it found a lack of jurisdiction, and left it open to Hindustan Zinc to pursue any other legal remedy available to it.

Lesson Learnt

Consenting to an arbitrator's appointment does not cure a fundamental lack of jurisdiction: a party can challenge the very authority of an arbitrator (or any adjudicator) at any later stage, because a decision rendered without jurisdiction is treated as void from the start, not merely voidable.

Arbitration & Commercial LawDelhi High Court

Gaurav Enterprises vs. Commissioner, Transport Department

Despite the Department's objection, the Court allowed the decree holder to withdraw its own petition, with liberty to file it again later if needed, subject to resolving any applicable stamp-duty requirements under the Indian Stamp Act, consistent with the Court's own precedent on that point.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

CA Deepak Gupta vs. CA Shubham Jain

The Court sent the matter to the Delhi High Court's Mediation and Conciliation Centre (SAMADHAN) for three weeks, while simultaneously appointing a named Sole Arbitrator to take over if mediation fails, so the arbitration process can begin immediately without a second round of court proceedings, subject to the arbitrator's standard independence disclosures and the Delhi International Arbitration Centre's rules and fees.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Freecharge Payment Technologies Pvt Ltd vs. Frederica Marketing Pvt Ltd

In light of the settlement, the Court allowed the decree holder to withdraw the enforcement petition, but expressly preserved its right to revive the same petition later if Frederica Marketing fails to honour the settlement's terms.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Arcis Clean Energy Pvt. Ltd. v. Parshva Innovation

The Supreme Court examined the Agreement as a whole to determine which city was the true "juridical seat" of arbitration, as opposed to merely a convenient venue for hearings, and concluded, based on the Agreement's language and structure, that Goa was the juridical seat. Since the juridical seat determines which court has supervisory jurisdiction over the arbitration, the Court held that the Delhi High Court lacked jurisdiction to have entertained the Section 11(6) application in the first place. It set aside the High Court's order and left the parties free to pursue the correct remedy before the appropriate court.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Hemant D. Shah HUF & Anr. v. Chittaranjan D. Shah HUF & Ors.

The Supreme Court held that whether someone is a "veritable party" to an arbitration, someone whose rights are substantially affected even without having signed the arbitration agreement, depends on the specific facts, and cannot be reduced to a rigid formula. On the facts here, it found the 3rd and 4th respondents to be veritable parties, since the validity of the 2009 partnership deed (and therefore their own rights) depended on whether the appellants' earlier retirement was itself valid. The Court made clear this finding was only a prima facie one for the purpose of deciding who should be part of the arbitration, and that the separate questions of limitation and estoppel raised by those respondents remain fully open for the Arbitral Tribunal itself to decide.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Union of India vs. Swadeshi Civil Infrastructure Pvt. Ltd.

The Court upheld the bonus award, holding that a contractual clause excluding certain delay-extension grounds from bonus eligibility only barred the contractor from claiming "damages" for those delays, not from earning the bonus if the project still finished ahead of schedule. It also declined to interfere with the tribunal's GST-reimbursement direction, since it merely required reimbursement where GST was actually payable. However, it set aside the interest awarded on a separate claim because the contractor had never actually asked for interest on that specific claim, making that part of the award legally invalid and severable from the rest.

Decided 12 Oct 2026Read case