I.K. Merchants Pvt. Ltd. v. The State of Rajasthan

Civil Appeal · 2025 INSC 418Decided 1 Apr 2025
Civil Appeal Nos.4560-4563 of 2025 (arising out of SLP(C) Nos.11779-11782 of 2022)
Justice J.B. Pardiwala · Justice R. Mahadevan

Background

In 1973, the appellants' shares in a mining company (originally Bikaner Gypsums Ltd., later Rajasthan State Mines and Minerals Ltd.) were compulsorily transferred to the State Government of Rajasthan. Disputing the fairness of the valuation, the appellants sued in 1978, and after decades of litigation (including a court-appointed valuer, multiple rounds before the Calcutta High Court, and an earlier remand by the Supreme Court itself) the share value was finally fixed at Rs.640 per share. By the time this appeal reached the Supreme Court, only one issue remained: what rate of interest the State should pay for the roughly 50-year delay in paying the appellants their due compensation.

Decision Breakdown

The Court held that where a decree involves payment of money and there is no contractual interest rate, Section 34 of the CPC governs, and courts have discretion (guided by fairness and equity, not mechanical application) to fix a reasonable rate for the period before suit, during the suit, and post-decree. It rejected the appellants' demand for 18% interest with quarterly rests as excessive and punitive, noting interest is compensatory (for the "time value of money"), not a penalty. Balancing the extraordinary 50-year delay and the fact that the entire burden fell on the State exchequer, the Court fixed simple interest at 6% per annum from 8 July 1975 until the date of the decree, and 9% per annum from the decree until actual payment, to be paid within two months.

Lesson Learnt

When the government (or anyone) delays paying money it legally owes you, courts will compensate you with interest for the lost "time value" of that money, but the interest rate must be reasonable and equitable, not punitive, and is fixed case-by-case rather than at whatever rate the claimant demands.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case