Indian Railway Construction Company Limited vs M/s National Buildings Construction Corporation Limited

Civil Appeal · 2023 INSC 248Decided 17 Mar 2023
Civil Appeal No. 8460 of 2022
M.R. Shah · M.M. Sundresh

Background

IRCON awarded NBCC a contract to construct a railway station-cum-commercial complex at Vashi, Navi Mumbai. NBCC failed to complete the work on time, and after supplementary agreements and advances did not resolve the delay, IRCON terminated the contract in 1994. The dispute went to arbitration, where the Arbitral Tribunal rejected two of NBCC's claims for refund of security deposits (Claim Nos. 33 and 34) and partly allowed IRCON's counter-claim for interest on advances given to NBCC. NBCC challenged the award before the Delhi High Court, which set aside the rejection of the security-deposit claims and the 18% interest awarded on an equipment advance; both the Single Judge and the Division Bench ruled in NBCC's favour, prompting IRCON's appeal to the Supreme Court.

Decision Breakdown

The Supreme Court held that the High Court, acting under Section 34 (and in appeal under Section 37) of the Arbitration Act, had exceeded its limited jurisdiction by re-appreciating the merits of a well-reasoned arbitral award instead of confining itself to the narrow grounds on which an award can be set aside. It restored the Arbitral Tribunal's rejection of NBCC's Claim Nos. 33 and 34 (return of security deposits), holding the High Court had no basis to interfere. On the interest issue, the Court held that under Section 31(7)(a) of the Arbitration Act an arbitrator may award pendente lite interest unless expressly barred by the contract, and since there was no such express bar, the Tribunal was entitled to award interest on the equipment-hypothecation advance; however, it reduced the rate from 18% to a more reasonable 12% per annum. The appeal was accordingly allowed to this extent, with no order as to costs.

Lesson Learnt

Courts reviewing an arbitral award under Sections 34/37 of the Arbitration Act cannot re-examine the merits of the arbitrator's findings as if hearing a fresh appeal: their power to interfere is narrow; and an arbitrator can award interest on sums due unless the contract specifically and clearly bars it.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case