K. Marappan (Dead) Through Sole LR. Balasubramanian v. The Superintending Engineer, T.B.P.H.L.C. Circle, Anantapur

Civil Appeal · 2019 INSC 406Decided 27 Mar 2019
Civil Appeal Nos. 159-170 of 2010
Chief Justice Ranjan Gogoi · Justice Sanjay Kishan Kaul · Justice K.M. Joseph

Background

A contractor was awarded irrigation-work contracts by the Andhra Pradesh state government in 1978-79 and later raised several monetary claims (for extra transport/"lead" costs, shortfalls in government-supplied food grains and cement, and interest) through arbitration after disputes arose over the work. An arbitrator awarded him amounts on several of these claims in 1988, but on challenge the trial court (Sub-Court) set aside or modified some of these awards, and the High Court went further, holding that the entire arbitration awards were unsustainable because they fell foul of Clause 59 of the contract (which barred compensation claims arising from delay/hindrance, though it allowed time extensions). The contractor's legal heir appealed to the Supreme Court after the contractor's death.

Decision Breakdown

The Supreme Court clarified the scope of Clause 59, holding that it barred only claims for compensation arising from delay or hindrance to the work, not claims, like Claim No.1, for the distinct extra cost of being forced to quarry stone/metal from a farther site than the one specified in the contract, which was not really a "delay" claim at all. The Court held the High Court erred in sweepingly treating all claims as barred by Clause 59. Examining the limited grounds on which a court can modify an arbitral award under Sections 15-16 of the Arbitration Act, 1940, the Court found no proper basis to interfere with the arbitrator's award on Claim No.1 (extra lead) and restored it along with the arbitrator-awarded interest, relying on precedent that an arbitrator has the discretion to award pendente lite interest. The Court accordingly partly allowed the appeals, restoring Claim No.1 and its interest, while not disturbing the rejection of the claims the appellant did not press (Claim Nos. 2 and 5) and the outcomes on the remaining contested claims.

Lesson Learnt

Courts reviewing an arbitration award have very limited power to interfere with or modify it (only for clerical errors, matters outside the reference, or similar narrow defects): they cannot reappraise the merits; and a contractual clause barring "delay" claims does not automatically bar a genuinely different claim (like extra cost from a changed worksite) just because it arose during an extended contract period.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case