Kaikara Construction Company v. State of Kerala
Background
A road contractor and the State disputed progress, withheld payments and extensions of time. The contract documents contained conflicting provisions about arbitration and appointment of a dispute-review expert. The High Court refused to appoint an arbitrator, but the parties later jointly proposed a retired High Court judge.
Decision Breakdown
The Court set aside the High Court order and referred the dispute to retired Justice K. John Mathew on the parties' mutual agreement. It expressly avoided deciding the competing arguments about the original contract's arbitration provisions. The parties were to negotiate and settle the terms of arbitration, with early completion expected. The contractor's payment claim and responsibility for delay remained to be resolved in that process.
Lesson Learnt
Parties may agree on arbitration to resolve a contract dispute even while contesting the original dispute-resolution terms. An order appointing an arbitrator does not establish that the contractor's claim is payable.