Background

In 1981, the Kerala State Electricity Board (KSEB) contracted with Kurien E. Kalathil to build a dam; after a 1983 government notification raised minimum wages, the contractor claimed labour-escalation charges, which led to decades of litigation across an industrial tribunal, the Kerala High Court, and an earlier Supreme Court appeal (settling the interest rate at 9% on one component, Ex.P20). Years later, the contractor returned to the High Court to enforce payment and claim additional amounts, including for extra work under a separate claim (Ex.P59); the High Court ordered KSEB to pay roughly Rs. 12.9 crore with interest and, with the parties' consent, referred a disputed slice of the claim to a sole arbitrator even though the parties had no arbitration agreement in their original contract.

Decision Breakdown

The Supreme Court set aside the High Court's judgment and substantially reworked the money due. It held that under the earlier judgment (Ex.P20), payments already made by KSEB had to be credited first against the principal and only then against interest (as the contractor's own documents showed), so the High Court's additional direction to pay further "principal" under Ex.P20 was wrong; it also held that, absent any direction for subsequent/future interest in the earlier judgments, Section 34(2) of the Code of Civil Procedure barred the contractor from claiming such future interest on either the Ex.P20 or Ex.P59 claims. Crucially, the Court held that because the parties had no arbitration agreement and had not jointly applied for arbitration, the High Court was wrong to refer the additional-work dispute (Ex.P59) to a sole arbitrator at all, and set aside both that arbitral award and the arbitration reference itself. It directed that amounts already paid be treated as full and final settlement of the Ex.P59 claims, with each side bearing its own costs.

Lesson Learnt

A court cannot send a contractual dispute to arbitration simply because it seems convenient: arbitration requires either a pre-existing arbitration agreement between the parties or their genuine joint consent, and courts (and litigants) must also track precisely how earlier payments are to be credited against principal versus interest, since miscalculating this can upend even a decades-old settled claim.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case