Kolkata West International City Pvt Ltd v. Devasis Rudra
Background
The respondent had paid over Rs. 39 lakh to the appellant developer in 2006 under an agreement promising possession of a row house by mid-2009 (with a grace period). When possession was not delivered, he filed a consumer complaint in 2011 seeking possession or, alternatively, a refund with interest and compensation. The State Consumer Commission and the National Consumer Disputes Redressal Commission (NCDRC) both ruled in his favour, directing a refund with 12% interest, and the developer appealed to the Supreme Court arguing that a completion certificate had since been obtained and possession had effectively been offered.
Decision Breakdown
The Supreme Court held that a buyer cannot be expected to wait indefinitely for possession, and that by the time the developer claimed to have completed construction, nearly seven years had passed beyond the promised date, well beyond what is reasonable. The Court also noted the agreement was one-sided, charging buyers 18% interest for default while capping the developer's liability for delay at a mere bank savings rate, reinforcing that the refund remedy was justified despite possession being the buyer's primary prayer. The Court upheld the refund order but reduced the interest rate from 12% to 9% per annum, otherwise affirming the NCDRC's directions, and disposed of the appeal with no order as to costs.
Lesson Learnt
Homebuyers are not bound to wait indefinitely for a developer to deliver possession, after a reasonable period of delay, they are entitled to seek a refund with interest, even if their complaint initially sought possession as the first choice of relief.