Kurukshetra Expressway Private Limited vs. National Highways Authority of India

First Appeal from Order (Original Side, Commercial) · 2026:DHC:8381-DBDecided 28 Sept 2026New Delhi Bench
FAO(OS) (COMM) 211/2026CNR: DLHC010371002026
Justice Anil Kshetarpal · Justice Shail Jain

Background

Kurukshetra Expressway had a 28-year concession from NHAI to four-lane a stretch of NH-71 in Haryana. Citing prolonged toll suspension caused by the Farmers' Agitation and COVID-19 (an "Indirect Political Force Majeure Event"), the company terminated the concession agreement in 2021 and demanded a large Termination Payment. An Arbitral Tribunal awarded it Rs. 911.13 crore, computing this using a higher project-cost figure the company had itself notified to NHAI. NHAI challenged this award in court, and a Single Judge cut down the award, holding that the contract capped the relevant project cost at Rs. 650 crore. Kurukshetra Expressway appealed that decision.

Decision Breakdown

The Division Bench dismissed the appeal and upheld the Single Judge's ruling. It held that a court's power to review an arbitral award (and, even more so, an appeal against that review) is very narrow: it can only check whether the Arbitral Tribunal's interpretation of the contract was one no reasonable person could adopt, not re-decide who has the better reading. Applying that standard, the Court agreed that the Tribunal had effectively rewritten the contract rather than interpreted it: the agreement's definition clause capped the relevant project cost at Rs. 650 crore, and a unilateral notification (a "disaggregation letter") by the company could not lawfully be used to inflate that contractually fixed ceiling.

Lesson Learnt

In commercial contracts, especially government infrastructure concessions, an express, clearly worded cost cap or ceiling is enforceable as written and cannot be enlarged simply because one party later claims its actual costs were higher; and Indian courts reviewing arbitral awards (under Sections 34/37 of the Arbitration Act) will not substitute their own view of the contract merely because another reading is possible.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case