Kurukshetra Expressway Private Limited vs. National Highways Authority of India

First Appeal from Order (Original Side, Commercial) · 2026:DHC:8381-DBDecided 28 Sept 2026New Delhi Bench
FAO(OS) (COMM) 211/2026CNR: DLHC010371002026
Justice Anil Kshetarpal · Justice Shail Jain

Background

Kurukshetra Expressway had a 28-year concession from NHAI to four-lane a stretch of NH-71 in Haryana. Citing prolonged toll suspension caused by the Farmers' Agitation and COVID-19 (an "Indirect Political Force Majeure Event"), the company terminated the concession agreement in 2021 and demanded a large Termination Payment. An Arbitral Tribunal awarded it Rs. 911.13 crore, computing this using a higher project-cost figure the company had itself notified to NHAI. NHAI challenged this award in court, and a Single Judge cut down the award, holding that the contract capped the relevant project cost at Rs. 650 crore. Kurukshetra Expressway appealed that decision.

Decision Breakdown

The Division Bench dismissed the appeal and upheld the Single Judge's ruling. It held that a court's power to review an arbitral award (and, even more so, an appeal against that review) is very narrow: it can only check whether the Arbitral Tribunal's interpretation of the contract was one no reasonable person could adopt, not re-decide who has the better reading. Applying that standard, the Court agreed that the Tribunal had effectively rewritten the contract rather than interpreted it: the agreement's definition clause capped the relevant project cost at Rs. 650 crore, and a unilateral notification (a "disaggregation letter") by the company could not lawfully be used to inflate that contractually fixed ceiling.

Lesson Learnt

In commercial contracts, especially government infrastructure concessions, an express, clearly worded cost cap or ceiling is enforceable as written and cannot be enlarged simply because one party later claims its actual costs were higher; and Indian courts reviewing arbitral awards (under Sections 34/37 of the Arbitration Act) will not substitute their own view of the contract merely because another reading is possible.

Arbitration & Commercial LawSupreme Court of India

Shreeram Builders v. Upendra Kantilal Thanawala & Ors.

The Supreme Court upheld setting aside the award, though for more precise reasons, holding that stamp duty classification alone wasn't decisive, but the arbitrators had exceeded their authority by effectively rewriting the contract: the price was never fixed, full consideration was never paid by deadline, and the arbitrators invented an unexplained price multiplier and damages the contract never provided for. Invoking its Article 142 power to do complete justice, the Court ordered the owners to refund all amounts received from the builder with 9% interest, since they never returned the payments after terminating the deal.

Decided 29 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S S.R. Ashok & Associates vs. Delhi Development Authority & Anr. and connected matters

The Court rejected the time-bar argument since the arbitration invocation was a single continuing one and DDA had consented to delays while participating throughout. It found no error apparent on the face of either award, upholding both and making them enforceable court decrees.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Axis Finance Ltd vs. Mr Nikhil A V & Ors.

The Court granted leave and liberty to withdraw and dismissed the petition without ruling on the underlying dispute.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

MMTC Limited vs. Aust Grain Exports Pty Ltd

The Court rejected MMTC's procedural and compensation arguments but found one real flaw: the tribunal had expressly rejected the exporter's claim for interest on the refunded guarantee (since the contract barred it), yet then awarded that very interest anyway, a direct, unexplained contradiction. The Court struck out only that contradictory portion as severable, leaving the rest of the award intact.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Chief Electoral Officer & Anr. vs. M/S Mahlakshmi Light House

The government argued the arbitrator ignored an internal inquiry suggesting inflated bills. The Court held returning officers who checked goods at the time gave more reliable evidence than a later inquiry report, and this specific objection was never raised before the single judge, so couldn't be raised for the first time on appeal. The appeal was dismissed.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Utracon Corporation Pte Ltd vs. Ucon PT Structural System Private Limited (formerly Utracon Structural Systems Private Limited) & Ors.

The defendant applied to refer the whole suit to arbitration, arguing the real dispute was about contractual rights to use the marks between identified parties (not a trademark registration or grant dispute, which can't be arbitrated), flowing from a single composite transaction. The Court agreed: the arbitration clause's existence was undisputed, the dispute was essentially contractual, and since the plaintiff itself had pleaded that the other defendants formed a "single economic unit" with the main defendant and derived their rights "through" it, their claims couldn't be separated out either; any question of whether they were bound by the arbitration clause was for the arbitrator to decide. The Court referred the whole suit to arbitration and disposed of it, expressly offering no opinion on the merits.

Decided 28 Oct 2026Read case
Kurukshetra Expressway Private Limited vs. National…