M. K. Construction vs. Maj. Gen. Hoshiar Singh (Retd) and Anr.

First Appeal from Order (Commercial) · 2026:DHC:8494-DBDecided 30 Sept 2026New Delhi Bench
FAO (COMM) 86/2023CNR: DLHC010123892023
Justice Avneesh Jhingan · Justice Shail Jain

Background

A building contractor appealed a decision upholding an arbitral award (passed after an earlier award was set aside and the matter sent back for a fresh local inspection) relating to a residential construction contract, including disputes over damages for delayed possession, adjustment of wood/gate costs, and compensation for mental harassment.

Decision Breakdown

The High Court dismissed the appeal, holding that an appeal under Section 37 has an even narrower scope than a challenge under Section 34: it cannot reopen factual findings or allow new arguments not raised at the earlier stage. The arbitrator's factual finding that certain wood had been supplied by the homeowner (justifying an adjustment against the contractor's bill) was reasonable and not interfered with; arguments about awards exceeding the pleaded claim or about the arbitrator's mandate having lapsed were raised for the first time on appeal and could not be entertained. The appeal was dismissed.

Lesson Learnt

When challenging an arbitral award through the courts, all objections must be raised at the first available stage (the Section 34 challenge): a later appeal cannot be used to introduce new grounds, and courts will not re-examine an arbitrator's reasonable factual findings.

Arbitration & Commercial LawSupreme Court of India

Shreeram Builders v. Upendra Kantilal Thanawala & Ors.

The Supreme Court upheld setting aside the award, though for more precise reasons, holding that stamp duty classification alone wasn't decisive, but the arbitrators had exceeded their authority by effectively rewriting the contract: the price was never fixed, full consideration was never paid by deadline, and the arbitrators invented an unexplained price multiplier and damages the contract never provided for. Invoking its Article 142 power to do complete justice, the Court ordered the owners to refund all amounts received from the builder with 9% interest, since they never returned the payments after terminating the deal.

Decided 29 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S S.R. Ashok & Associates vs. Delhi Development Authority & Anr. and connected matters

The Court rejected the time-bar argument since the arbitration invocation was a single continuing one and DDA had consented to delays while participating throughout. It found no error apparent on the face of either award, upholding both and making them enforceable court decrees.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Axis Finance Ltd vs. Mr Nikhil A V & Ors.

The Court granted leave and liberty to withdraw and dismissed the petition without ruling on the underlying dispute.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

MMTC Limited vs. Aust Grain Exports Pty Ltd

The Court rejected MMTC's procedural and compensation arguments but found one real flaw: the tribunal had expressly rejected the exporter's claim for interest on the refunded guarantee (since the contract barred it), yet then awarded that very interest anyway, a direct, unexplained contradiction. The Court struck out only that contradictory portion as severable, leaving the rest of the award intact.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Chief Electoral Officer & Anr. vs. M/S Mahlakshmi Light House

The government argued the arbitrator ignored an internal inquiry suggesting inflated bills. The Court held returning officers who checked goods at the time gave more reliable evidence than a later inquiry report, and this specific objection was never raised before the single judge, so couldn't be raised for the first time on appeal. The appeal was dismissed.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Utracon Corporation Pte Ltd vs. Ucon PT Structural System Private Limited (formerly Utracon Structural Systems Private Limited) & Ors.

The defendant applied to refer the whole suit to arbitration, arguing the real dispute was about contractual rights to use the marks between identified parties (not a trademark registration or grant dispute, which can't be arbitrated), flowing from a single composite transaction. The Court agreed: the arbitration clause's existence was undisputed, the dispute was essentially contractual, and since the plaintiff itself had pleaded that the other defendants formed a "single economic unit" with the main defendant and derived their rights "through" it, their claims couldn't be separated out either; any question of whether they were bound by the arbitration clause was for the arbitrator to decide. The Court referred the whole suit to arbitration and disposed of it, expressly offering no opinion on the merits.

Decided 28 Oct 2026Read case
M. K. Construction vs. Maj. Gen. Hoshiar Singh (Retd) and…