M.C. Mehta v. Union of India & Ors. (Kundli-Manesar-Palwal Expressway lenders' applications)

Interlocutory Application · Neutral citation not assigned (Interlocutory Application Nos. 363-364 of 2015 (IDBI Bank Ltd. and State Bank of India, Applicants) in Writ Petition (Civil) No. 13029 of 1985)Decided 13 May 2016
Interlocutory Application Nos. 363-364 of 2015 (IDBI Bank Ltd. and State Bank of India, Applicants) in Writ Petition (Civil) No. 13029 of 1985
Chief Justice T.S. Thakur · Justice R. Banumathi

Background

Within the long-running M.C. Mehta environmental PIL monitoring the Kundli-Manesar-Palwal Expressway project near Delhi, a consortium of lender banks (led by IDBI Bank and State Bank of India) had financed the original concessionaire building the expressway. When the original concessionaire failed to complete the project on time, the Supreme Court had earlier directed the Haryana state agency (HSIIDC) to replace it, and the work was split between two new entities. The lender banks approached the Court complaining that HSIIDC had gone ahead with the new concessionaires without honouring its contractual commitment to ensure the new entities took over the outstanding dues owed to the banks by the old concessionaire.

Decision Breakdown

The Court declined to itself rewrite the new concession agreements to force the new concessionaires to assume the old lenders' dues, holding that this would improperly vary contractual terms between other parties and was a dispute more suited to adjudication elsewhere. Noting that a tripartite agreement between the banks, HSIIDC and the old concessionaire already contained an arbitration clause, the Court referred all disputes between the lender banks, HSIIDC and the outgoing concessionaire to the arbitral tribunal already handling a related arbitration (headed by Justice N.K. Sodhi). As an interim protective measure pending that arbitration, it directed that 80% of toll revenue collected on the already-built stretch of the expressway be deposited in an escrow account with the lead bank, with the remaining 20% available to HSIIDC for maintenance, and directed that this arrangement not hold up the new concessionaire's construction work. The Court expressly clarified it was not expressing any view on the merits of the banks' underlying contractual claims, leaving those entirely to the arbitral tribunal.

Lesson Learnt

When a dispute is already covered by an arbitration clause in a contract, courts will generally decline to decide the merits themselves and will instead send the parties to arbitration, while still using their interim powers (such as directing an escrow account) to protect a party's financial interests until that arbitration concludes.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case