Mohammed Masroor Shaikh vs Bharat Bhushan Gupta & Ors.

Civil Appeal · 2022 INSC 138Decided 2 Feb 2022
Civil Appeal No. 874 of 2022
Indira Banerjee · Abhay S. Oka

Background

The appellant and the respondents were partners in three real-estate partnership firms. When one partner (respondent no. 1) retired from the firms under retirement deeds containing an arbitration clause, and later invoked arbitration over a dispute, the appellant did not respond. The Bombay High Court, acting on a Section 11 petition, appointed an arbitrator. The appellant challenged this appointment before the Supreme Court, claiming he was never properly served notice of the High Court proceedings (partly because he was hospitalised in mid-2021) and that the retirement deed's arbitration clause did not even cover disputes between a retiring and continuing partner.

Decision Breakdown

The Supreme Court dismissed the appeals. It found the appellant had in fact been served with an advocate's notice of the Section 11 petition back in 2019, well before his 2021 hospitalisation, so he had ample opportunity to contest it. It also noted the appellant's own advocate had appeared before the arbitrator and even supported another party's objections to arbitration, a fact the appellant had failed to disclose when filing the present appeals. Relying on its earlier ruling in Vidya Drolia v. Durga Trading Corporation, the Court held that at the Section 11 stage, courts should generally leave contested questions like whether a dispute is arbitrable or time-barred to the arbitrator to decide in the first instance, intervening only when it is manifestly clear on the face of it that there is no valid arbitration agreement. Since the High Court's order had expressly kept these issues open, and the appellant already had a pending challenge before the High Court under Section 34 of the Act, no interference was warranted.

Lesson Learnt

When a court is deciding merely whether to appoint an arbitrator, it need not resolve every dispute about the arbitration agreement's scope or limitation: those are ordinarily left for the arbitrator to decide first; also, litigants must disclose all material facts (like already having appeared before the arbitrator) when seeking relief from a court, or risk having that omission counted against them.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case