M/s Aravali Power Co. Pvt. Ltd. vs Vedprakash

Civil Appeal · 2022 INSC 547Decided 10 May 2022
Civil Appeal Nos. 1692-1693 of 2020
D.Y. Chandrachud · Pamidighantam Sri Narasimha

Background

This batch of appeals arose from several National Green Tribunal (NGT) orders concerning thermal power plants' failure to properly dispose of and utilise fly ash, the ash residue from burning coal, as required by statutory notifications under the Environment (Protection) Act, 1986. Specifically, Civil Appeal Nos. 1692-1693 of 2020 was Aravali Power Company's challenge to an NGT order dismissing a review of an earlier direction requiring remedial action against the company for improper fly-ash disposal that allegedly harmed nearby agricultural land. While the batch of appeals was pending in the Supreme Court, the Union Ministry of Environment, Forest and Climate Change issued a fresh notification on 31 December 2021 superseding the older fly-ash notifications and prescribing new timelines (including specifically for "legacy ash" (previously accumulated, unutilised ash)) for compliance.

Decision Breakdown

The Supreme Court held that this new December 2021 notification fundamentally altered the regulatory basis on which the various NGT orders (which had been based on the older, superseded notifications and deadlines) had found the thermal power plants non-compliant and imposed environmental compensation. Since the very foundation of the NGT's findings had been overtaken by the new rules, the Court set aside all the impugned NGT orders across the entire batch of appeals, including the one concerning Aravali Power. It also directed the Ministry to review whether the new notification needs further modification to align with the Hazardous Waste Management Rules, 2016, and to ensure the notification's own monitoring, audit, and enforcement mechanisms are actually put in place within three months. The Court expressly clarified that this was not a ruling on the merits or validity of the new notification itself, leaving any party aggrieved by it free to challenge it separately.

Lesson Learnt

When the law or regulatory framework underlying a tribunal's order changes significantly while an appeal is pending, courts may set aside the earlier order as having lost its legal foundation, rather than deciding the original dispute on its old facts, but this is not the same as ruling that everyone is now off the hook, since the new rules and compliance obligations still apply going forward.

Environmental LawDelhi High Court

Pradeep Kumar Gupta vs. Delhi Development Authority

The Division Bench dismissed the appeal. It held that unauthorised parking itself is a misuse of the regulated floodplain, regardless of whether any dumping occurred. The Rs 5,000 compensation under the NGT's para 94(vi)(d) relates to throwing pooja or other material into the river, not to parking, so it did not apply. The lack of parking space due to renovation did not justify parking in a prohibited, environmentally sensitive area. The appellant had been given a personal hearing on its representation before the rejection order, so the no-hearing complaint also failed.

Decided 1 Oct 2026Read case
Environmental LawDelhi High Court

M/s Carnival Greens vs. Delhi Pollution Control Committee & Ors.

This was a very short, procedural order. The DPCC's counsel confirmed to the Court, on instructions, that only a show-cause notice had been issued so far and that the petitioner would be given a personal hearing before the DPCC decided anything. On the strength of this assurance being placed on record, the Court disposed of the writ petition without deciding any of the substantive issues raised (about infrastructure gaps or a provisional consent), since the DPCC had committed to hearing the petitioner out first.

Decided 18 Sept 2026Read case
Environmental LawDelhi High Court

M/S Ambria Cafe vs. Delhi Pollution Control Committee (DPCC) & Ors.

Notice was issued in the petition, and counsel for DPCC accepted notice on its behalf. DPCC's counsel clarified, on instructions, that only a show cause notice (not a final closure/compensation order) had been issued, and assured the Court that the petitioner would be given a personal hearing before any final decision was taken. Taking this statement on record, the Court disposed of the writ petition without deciding the underlying merits.

Decided 18 Sept 2026Read case
Environmental LawSupreme Court of India

M/S Punahchakran Private Limited v. Indotech Waste Solution

The Supreme Court held that the CPCB's 2016 revised guidelines for bio-medical waste facilities are mandatory and binding even though never published in the Official Gazette, since publication on the CPCB's official website was a reasonably sufficient mode of notice for such technical guidelines. However, the Court found that Punahchakran's relaxation from the standard 1-acre land requirement was validly granted: its facility was in a rural area (a permitted ground for relaxation) and the CPCB had been properly consulted and had imposed additional safeguard conditions. The Court also clarified that land allotment is not a strict legal precondition for starting the environmental-clearance application process, and that the original 2021 Terms of Reference remained valid (having a four-year validity period) even though the first EC based on it was earlier quashed, so the second EC could validly rely on that same original study. Concluding that the NGT had erred in quashing the second EC and CTE, the Supreme Court set aside the NGT's judgment and restored Punahchakran's approvals.

Decided 7 Sept 2026Read case
Environmental LawSupreme Court of India

Fisherman Care v. Government of India, Department of Animal Husbandry, Dairying and Fisheries

The Supreme Court held there is no real conflict between the Centre's power to regulate fishing in the EEZ (under Entry 57 of List I, exercised via the new EEZ Rules, 2025) and the State's power to regulate fishing within its territorial waters (under Entry 21 of List II, via the Tamil Nadu Marine Fishing Regulation Rules): these are two co-equal, autonomous legislative spheres that must operate together through "cooperative federalism." Following the Expert Committee's recommendations (that an outright ban on purse seine nets isn't justified but effective regulation is needed), the Union had already notified the EEZ Rules, 2025 creating an "Access Pass" system for vessels to transit through State waters into the EEZ. However, the Court found the on-ground implementation deeply flawed: of 257 access-pass applications, 226 were stuck pending verification by Tamil Nadu authorities, with only 6 passes actually issued, the lowest among all coastal States, which the Court said effectively amounted to an unwritten, unlawful ban. The Court directed Tamil Nadu to process applications efficiently and to frame rules designating a specific transit channel through its territorial waters for vessels headed to the EEZ, and disposed of the application on this basis.

Decided 2 Sept 2026Read case
Environmental LawSupreme Court of India

In Re: 2 Million Lives at Risk, Contamination in Jojari River, Rajasthan

Reviewing the SIT's report and the State's compliance report, the Court found continuing systemic failures, including that the State's report was silent on any action taken against responsible Rajasthan State Pollution Control Board officers, and issued a fresh set of detailed directions. These included: a scientific determination and demarcation of the High Flood Line and ecological buffer for the river system before any further industrial development (specifically flagging the proposed RIICO Industrial Area, Kakani, and the Ambey Valley Industrial Park as built too close to the river); an inquiry by the Chief Secretary into irregularities in land-use conversion and plot allotments at Ambey Valley; a comprehensive groundwater management strategy with a ban on new water-intensive industries in over-exploited "dark zones"; expedited transfer of identified lands to the Forest Department for ecological restoration; and a survey-and-removal drive against encroachments and illegal mining on riverbeds and floodplains. The Court also directed that action taken against RSPCB officers be reported within three days and listed the matter for further hearing on 22 September 2026, while noting that industrial pollution issues in Jaipur would be taken up separately once the present remedial framework is substantially implemented.

Decided 7 Aug 2026Read case