M/S Awadhesh Singh Gautam v. State of Chhattisgarh & Ors.

Civil Appeal · 2026 INSC 1072Decided 30 Sept 2026
Civil Appeal arising out of SLP(C) No. 10464 of 2026 with connected appeals
Justice Pamidighantam Sri Narasimha · Justice Alok Aradhe

Background

A contracting firm was awarded three road-construction packages under the Pradhan Mantri Gram Sadak Yojana and had completed about 40% of the work, but the government withheld payment of running bills worth over ₹1 crore. The State separately alleged the firm had been overpaid on two earlier, unrelated road contracts (now the subject of a departmental inquiry and criminal proceedings), and issued a recovery order deducting that disputed amount directly from the money due under the three new contracts. The High Court dismissed the firm's writ petitions challenging this deduction.

Decision Breakdown

The Supreme Court quashed the recovery order and directed the government to release the withheld ₹84,17,003 with 6% annual interest. It held that the contract clause governing recovery required prior notice to the contractor and specific approval from the CEO of the road agency before any deduction, neither of which had been obtained, and that an unproven, disputed overpayment claim from an entirely separate contract cannot simply be treated as an ascertained debt and unilaterally adjusted against money owed under a different, unrelated contract. The Court clarified this ruling only addressed the legality of how the recovery was carried out, and does not affect the pending criminal case or the State's ability to pursue the alleged overpayment through proper legal channels.

Lesson Learnt

A government authority cannot bypass a contract's own procedural safeguards, like prior notice and a designated approving officer, to recover a disputed, unproven claim by simply withholding payments legitimately due under a separate contract.

Arbitration & Commercial LawSupreme Court of India

Shreeram Builders v. Upendra Kantilal Thanawala & Ors.

The Supreme Court upheld setting aside the award, though for more precise reasons, holding that stamp duty classification alone wasn't decisive, but the arbitrators had exceeded their authority by effectively rewriting the contract: the price was never fixed, full consideration was never paid by deadline, and the arbitrators invented an unexplained price multiplier and damages the contract never provided for. Invoking its Article 142 power to do complete justice, the Court ordered the owners to refund all amounts received from the builder with 9% interest, since they never returned the payments after terminating the deal.

Decided 29 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S S.R. Ashok & Associates vs. Delhi Development Authority & Anr. and connected matters

The Court rejected the time-bar argument since the arbitration invocation was a single continuing one and DDA had consented to delays while participating throughout. It found no error apparent on the face of either award, upholding both and making them enforceable court decrees.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Axis Finance Ltd vs. Mr Nikhil A V & Ors.

The Court granted leave and liberty to withdraw and dismissed the petition without ruling on the underlying dispute.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

MMTC Limited vs. Aust Grain Exports Pty Ltd

The Court rejected MMTC's procedural and compensation arguments but found one real flaw: the tribunal had expressly rejected the exporter's claim for interest on the refunded guarantee (since the contract barred it), yet then awarded that very interest anyway, a direct, unexplained contradiction. The Court struck out only that contradictory portion as severable, leaving the rest of the award intact.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Chief Electoral Officer & Anr. vs. M/S Mahlakshmi Light House

The government argued the arbitrator ignored an internal inquiry suggesting inflated bills. The Court held returning officers who checked goods at the time gave more reliable evidence than a later inquiry report, and this specific objection was never raised before the single judge, so couldn't be raised for the first time on appeal. The appeal was dismissed.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Utracon Corporation Pte Ltd vs. Ucon PT Structural System Private Limited (formerly Utracon Structural Systems Private Limited) & Ors.

The defendant applied to refer the whole suit to arbitration, arguing the real dispute was about contractual rights to use the marks between identified parties (not a trademark registration or grant dispute, which can't be arbitrated), flowing from a single composite transaction. The Court agreed: the arbitration clause's existence was undisputed, the dispute was essentially contractual, and since the plaintiff itself had pleaded that the other defendants formed a "single economic unit" with the main defendant and derived their rights "through" it, their claims couldn't be separated out either; any question of whether they were bound by the arbitration clause was for the arbitrator to decide. The Court referred the whole suit to arbitration and disposed of it, expressly offering no opinion on the merits.

Decided 28 Oct 2026Read case
M/S Awadhesh Singh Gautam v. State of Chhattisgarh & Ors.