Background

A Swiss arms manufacturer had a 2012 contract with India's Ministry of Defence to supply sub-machine guns. In 2016, the Ministry encashed the company's bank guarantee and deducted liquidated damages for delayed supply, rejecting the company's objections. The parties then continued informal "bilateral discussions" for years, but in 2017 the Ministry told the company it would not reconsider its decision. The company sent a formal notice invoking arbitration only in November 2021, more than five years after the 2016 deduction, and then approached the Supreme Court under Section 11(6) of the Arbitration and Conciliation Act asking it to appoint an arbitrator, arguing that the ongoing negotiations should extend the limitation period.

Decision Breakdown

The Supreme Court held that time-barred claims cannot be referred to arbitration merely by invoking Section 11(6), and that the "cause of arbitration" accrues just like a cause of action in civil litigation, from the date of the clear and unequivocal breach, not from whenever negotiations eventually break down. Relying on its own precedent (Geo Miller) and English arbitration law commentary, the Court found the actual "breaking point" was 2016, when the bank guarantee was encashed and liquidated damages deducted (an unequivocal, final action) not the company's later claim that negotiations continued informally until 2019. Mere ongoing talks, without a specifically pleaded and evidenced history of genuine negotiation, cannot indefinitely extend the three-year limitation period under the Limitation Act, 1963. Since the arbitration notice was issued more than five years after the cause of action arose, the Court held the claim was "hopelessly barred" by limitation and rejected the petition for appointment of an arbitrator.

Lesson Learnt

A party to a contract with an arbitration clause must invoke arbitration within the statutory limitation period (generally three years) from when the dispute clearly and finally crystallizes, continuing informal negotiations or correspondence after that point does not pause or restart the clock, so parties should send a formal arbitration notice promptly once a dispute becomes final rather than relying on ongoing talks to preserve their rights.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case