M/S Bhandari Udyog Ltd v. Industrial Facilitation Council

Civil Appeal · Neutral citation not assigned (Civil Appeal No. 2077 of 2015)Decided 20 Feb 2015
Civil Appeal No. 2077 of 2015
Justice M.Y. Eqbal · Justice Kurian Joseph

Background

The appellant, a small-scale cotton business based in Raichur, Karnataka, sold 750 bales of cotton to a spinning mill (respondent no.2) in Latur, Maharashtra, which paid only part of the price. The appellant obtained an arbitration award from the Industrial Facilitation Council (IFC), Bangalore (appointed via a Section 11 application before the Karnataka High Court) directing the mill to pay the balance with interest. The mill challenged the award under Section 34 of the Arbitration Act before the District Court at Latur, and when the appellant objected to that court's jurisdiction, the District Judge and later the Bombay High Court both held that the Latur court had jurisdiction since the mill resided and received the goods there.

Decision Breakdown

The Supreme Court held that because the arbitration was conducted within the jurisdiction of the Raichur court (which was subordinate to the Karnataka High Court that had entertained the Section 11 application), under Section 42 of the Arbitration Act only a court subordinate to that same High Court could entertain a challenge to the award, not a court under the Bombay High Court. Relying on its own recent three-judge bench ruling in State of West Bengal v. Associated Contractors (2015) on Section 42's effect, the Court found that the District Court at Latur and the Bombay High Court had both erred in law by entertaining and upholding jurisdiction over the Section 34 application. It allowed the appeal and set aside the Bombay High Court's order, with no order as to costs.

Lesson Learnt

Under Section 42 of the Arbitration and Conciliation Act, once one court has been approached in connection with an arbitration (e.g., for appointing an arbitrator), all subsequent applications relating to that arbitration, including a challenge to the award, must go to that same court or its superior court, not to a court closer to where the other party happens to reside or where goods were delivered.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case