M/s C and C Constructions Ltd. v. IRCON International Ltd.

Civil Appeal · 2025 INSC 138Decided 31 Jan 2025
Civil Appeal No. 6657 of 2023
Justice Abhay S. Oka · Justice Ujjal Bhuyan

Background

The appellant construction company was contracted by the respondent (IRCON) to build road-over-bridges in Rajasthan, but the work was delayed for reasons the appellant blamed on the respondent. The appellant repeatedly sought and was granted extensions of time, and in doing so gave written undertakings that it would not claim anything beyond price escalation for the delay. Two years after the last such undertaking, the appellant invoked arbitration and claimed roughly Rs. 44 crores in damages; the Arbitral Tribunal rejected all claims based on a contract clause (49.5) barring damages claims for employer-caused delay, and this was upheld by a Single Judge and a Division Bench of the Delhi High Court.

Decision Breakdown

The Supreme Court held that clause 49.5 of the contract clearly barred any damages claim for delay attributable to the employer, entitling the contractor only to a time extension, and that the appellant's own conduct, repeatedly invoking the clause to seek extensions and giving written undertakings not to claim more than escalation, estopped it from later challenging the clause's validity. It also held that new arguments (validity under the Contract Act, and waiver of the clause) raised for the first time before the Supreme Court could not be entertained, and that in any event the respondent's correspondence never amounted to a waiver. Given the narrow scope of judicial review under Sections 34 and 37 of the Arbitration Act, the Court found no ground to interfere and dismissed the appeal.

Lesson Learnt

Parties who repeatedly invoke a contractual clause to their own benefit (e.g., to get extensions) and give written undertakings consistent with that clause cannot later turn around and challenge its validity, and courts reviewing arbitration awards under Sections 34/37 will not re-examine the merits, only whether the tribunal acted within its jurisdiction and the contract's terms.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case