M/S. Centrotrade Minerals and Metals Inc. v. Hindustan Copper Ltd.

Civil Appeal · 2020 INSC 411Decided 2 Jun 2020
Civil Appeal No. 2562 of 2006
Justice Rohinton Fali Nariman · Justice S. Ravindra Bhat · Justice V. Ramasubramanian

Background

Centrotrade, a U.S. company, sold copper concentrate to Hindustan Copper Ltd. (HCL) under a contract with a two-step arbitration clause: first an arbitration in India, and if either side was unhappy with that result, a second arbitration in London. The Indian arbitration produced a "Nil Award," so Centrotrade pursued the London arbitration, which awarded it a substantial sum. HCL resisted enforcement of the London award in Indian courts for nearly two decades, and the dispute had already reached the Supreme Court once before, resulting in a split decision between two judges that needed to be resolved by a larger Bench.

Decision Breakdown

The Supreme Court held that the two-tier arbitration clause was valid, and closely examined HCL's claim that it never got a fair chance to present its case in the London arbitration. Reviewing the actual correspondence, the Court found that the London arbitrator had in fact given HCL multiple extensions of time, and HCL's own prolonged refusal to participate, followed by late submissions, including after the 9/11 attacks in New York, which the arbitrator still considered, did not amount to any unfairness. The Court held that one of the two earlier Supreme Court judges hearing this dispute had made factual errors in criticizing the arbitrator. Centrotrade's appeal was allowed, HCL's appeal was dismissed, and the Court directed that the foreign (London) arbitration award must now be enforced in India.

Lesson Learnt

An arbitrator who gives a party repeated, generous opportunities to present its case is not at fault if that party chooses not to use them in time; and Indian courts enforcing a foreign arbitration award will not reopen or second-guess the arbitrator's fair handling of procedure.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case