M/S Construction & Design Services v. Delhi Development Authority

Civil Appeal · Neutral citation not assigned (Civil Appeal Nos. 1440-1441 of 2015, arising out of SLP (C) Nos.35365-35366 of 2012)Decided 4 Feb 2015
Civil Appeal Nos. 1440-1441 of 2015, arising out of SLP (C) Nos.35365-35366 of 2012
Justice T.S. Thakur · Justice Adarsh Kumar Goel

Background

DDA had awarded the appellant-contractor a contract in 1995 to construct a sewerage pumping station, with a clause stipulating liquidated damages of up to 1% per day of delay (capped at 10% of the estimated cost) if the work was not completed on schedule. The contractor worked at a slow pace and the contract was terminated in 1999, after which DDA levied over Rs.20 lakh in compensation for the delay. The dispute over whether this stipulated sum was an enforceable pre-estimate of damages or an unenforceable "penalty" reached the Supreme Court.

Decision Breakdown

The Court examined the law under Sections 73 and 74 of the Indian Contract Act on compensation for breach, noting that where exact loss is difficult to prove (as is common in construction contracts), a genuine pre-agreed estimate of damages in the contract should ordinarily be honoured unless shown to be unreasonable or a disguised penalty. Since the contractor (who committed the breach) led no evidence that DDA suffered no loss or that the clause was unreasonable, the Court held DDA was entitled to reasonable compensation for the delay. However, because DDA also did not produce specific evidence of the exact extent of loss, the Court adopted a middle path, holding it fair to award half of the claimed amount as reasonable compensation. The appeal was thus partly allowed, modifying the High Court's decree.

Lesson Learnt

A party that breaches a contract containing a genuine pre-agreed damages clause cannot escape liability simply by arguing there is no proof of exact loss: courts will enforce such clauses as a fair estimate of damages, though courts retain discretion to moderate the amount when neither side produces precise evidence of the loss actually suffered.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case