M/s Durga Welding Works vs. Chief Engineer, Railway Electrification

Civil Appeal · 2022 INSC 12Decided 4 Jan 2022
Civil Appeal No. 54 of 2022
Ajay Rastogi · Abhay S. Oka

Background

After disputes arose under a works contract, the appellant contractor served a notice in August 2009 seeking appointment of an arbitrator and, when the railway authorities did not act, filed a Section 11(6) petition before the High Court of Orissa in October 2009. The appellant then took no further steps to pursue that petition or notify the respondents of it; meanwhile it selected arbitrators from a panel offered by the railway, participated in the resulting arbitral proceedings, but later stopped participating, leading to an ex-parte award against it in June 2013. The High Court was informed of the pending Section 11(6) petition only in 2016, almost three years after the award, and it eventually dismissed the petition in 2019, leaving the appellant free to challenge the award under Sections 34/37.

Decision Breakdown

The Supreme Court reaffirmed the settled legal principle (from Datar Switchgears v. Tata Finance and Punj Lloyd v. Petronet MHB) that once a Section 11(6) application is filed before the High Court, the other party forfeits its right to unilaterally appoint an arbitrator, and only the High Court retains jurisdiction to do so. However, on the particular facts, the appellant had itself gone silent on its own petition for years, actively participated in selecting arbitrators and initially engaging with the Arbitral Tribunal, and alerted the High Court to its pending petition only long after an ex-parte award had already been passed. Given this conduct, the Court held the High Court committed no error in declining to appoint an arbitrator under Section 11(6) and dismissing the petition, while leaving the appellant free to challenge the ex-parte award through the statutory remedy. The appeal was accordingly dismissed.

Lesson Learnt

Merely filing a court petition to preserve a legal right is not enough: a party must diligently pursue it; conduct inconsistent with that petition (such as participating in a parallel arbitral process one later claims is invalid) can defeat relief even where the underlying legal principle would otherwise favour the applicant.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case