M/s Geo Miller & Co. Pvt. Ltd. v. Chairman, Rajasthan Vidyut Utpadan Nigam Ltd.

Civil Appeal · 2019 INSC 989Decided 3 Sept 2019
Civil Appeal No. 967 of 2010
Justice N.V. Ramana · Justice Mohan M. Shantanagoudar · Justice Ajay Rastogi

Background

A contractor had executed three water-treatment-plant work orders for a Rajasthan state power utility between 1979 and 1985, each containing an arbitration clause. After the contractor's bills went unpaid for years and settlement talks dragged on through the 1990s, it finally sought appointment of an arbitrator in 2002: roughly 14-19 years after the final bills were raised. The Rajasthan High Court dismissed the contractor's applications for appointment of an arbitrator as hopelessly time-barred, and the contractor appealed to the Supreme Court.

Decision Breakdown

The Supreme Court first clarified that because the request for arbitration was made (in substance) before the 1996 Arbitration and Conciliation Act's effective cut-off, the older 1940 Arbitration Act's limitation framework applied. On the central question of limitation, the Court held that the contractor had failed to plead or produce evidence showing that the parties' negotiations genuinely kept the dispute alive right up to the respondent's 1999 letter; absent such proof, limitation began running much earlier: at the latest from 1997, when the Settlement Committee failed to respond. The Court found the contractor's 14-year delay reflected sleeping on its rights rather than genuine ongoing negotiation, agreeing with the High Court that the claim appeared to be an opportunistic attempt to exploit the newer 1996 Act's longer window. All three appeals were accordingly dismissed and the High Court's judgment was confirmed.

Lesson Learnt

In contractual/arbitration disputes, simply exchanging correspondence with the other side does not indefinitely pause the limitation clock: a party must actively and promptly pursue its remedy (such as seeking an arbitrator) once a dispute crystallizes, or risk having years of delay held against it as "sleeping on one's rights."

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case