M/s Greater Ashoka and Land Development Company vs Kanti Prasad Jain (Deceased) Through LRs

Civil Appeal · 2023 INSC 1055Decided 6 Dec 2023
Civil Appeal Nos. 7990-7991 of 2023
Vikram Nath · Rajesh Bindal

Background

In 1963, the appellant company advertised residential plots in a Faridabad colony at Rs. 25 per square yard. The respondent paid partial booking money for a plot but never paid the balance. Over the following decades, two new state laws required the developer to obtain fresh permissions for the colony, delaying the project for years. In 1982, the developer offered the respondent a substitute plot at a much higher rate (Rs. 135 per square yard) but the respondent, instead of accepting or refusing outright, asked for clarifying details that were never furnished, then sent a legal notice demanding registration at the original 1963 rate. When nothing happened, he sued for specific performance (or, alternatively, refund with damages) in 1986: more than 20 years after the original booking.

Decision Breakdown

The trial court and, eventually, the High Court sided with the respondent and ordered execution of the sale deed at the original low rate. The Supreme Court found that after six decades of delay, changed circumstances, and the sheer rise in land values, forcing a sale at the 1963 price was neither fair nor practical, and noted that the respondent's own suit had itself pleaded refund of earnest money with damages as an alternative relief. Balancing the developer's admitted fault in the delay against the impracticality of enforcing a 60-year-old rate, the Court modified the High Court's decree: instead of registering the sale deed at Rs. 25 per square yard, the appellant was directed to pay the respondent a lump sum of Rs. 50,00,000 (fifty lakh rupees) within three months as full and final settlement.

Lesson Learnt

Courts retain the flexibility, even at the final appellate stage, to substitute a fair monetary settlement for literal specific performance of a decades-old contract when intervening circumstances (law changes, extreme delay, drastic value shifts) make the original bargain impractical to enforce as originally struck.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case