M/S Hindustan Construction Company Limited vs. M/S National Highways Authority of India

Not available · 2023 INSC 768Decided 24 Aug 2023
Not available
S. Ravindra Bhat · Aravind Kumar

Background

Highway construction contractors (including Hindustan Construction Company) and the National Highways Authority of India (NHAI) disputed how to measure and pay for embankment work built using a mix of soil and pond ash: the contractors said the entire cross-section should be measured together as one composite unit, while NHAI's engineer measured soil and pond ash separately. An arbitral tribunal largely ruled in the contractors' favour, a single judge upheld that award, but the Delhi High Court's Division Bench reversed it, holding the tribunal's interpretation was implausible. Several appeals with the same underlying contract-interpretation question reached the Supreme Court together.

Decision Breakdown

The Supreme Court held that under Section 34/37 of the Arbitration Act, courts have an extremely narrow scope to interfere with an arbitral award and cannot substitute their own interpretation of a contract clause just because another view is possible: interference is permitted only where the tribunal's view is one no fair-minded person could reasonably take. Since the embankment was in fact built as a single compacted composite structure and the tribunal's interpretation of the technical specification was a plausible reading of the contract, the High Court's Division Bench had overstepped by re-appraising the merits like an ordinary appeal. The Court also clarified, as a broader point of arbitration law, that a dissenting arbitrator's opinion cannot be elevated into the award itself if the majority award is set aside, since the dissent was never subjected to the same adversarial scrutiny. All the appeals were allowed, the arbitral awards restored, with only the interest rate on amounts due modified to a uniform 12%.

Lesson Learnt

Courts reviewing an arbitration award must resist the temptation to re-decide the underlying contractual dispute themselves; as long as the arbitrator's interpretation of the contract is a reasonable and plausible one, it must stand even if a court might have read the clause differently.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case