M/s IL&FS Tamil Nadu Power Company Limited vs T. Muruganandam & Ors.

Civil Appeal · 2023 INSC 136Decided 17 Feb 2023
Civil Appeal Nos. 1811-1812 of 2015
M.R. Shah · C.T. Ravikumar

Background

IL&FS Tamil Nadu Power Company obtained an Environmental Clearance in 2010 to build a large imported-coal thermal power plant (planned at 3600 MW) in Cuddalore district, Tamil Nadu. Local fishermen and their representatives challenged the EC. In May 2012 the NGT upheld the EC but suspended it until the Environment Ministry reviewed it in light of a cumulative impact study; the company did a "rapid" cumulative impact study instead, and in August 2012 the Ministry issued a corrigendum adding extra conditions, including installing a flue-gas desulphurisation (FGD) system. The fishermen appealed again, and in November 2014 the NGT quashed that corrigendum. The company appealed to the Supreme Court, which stayed the NGT order in 2015; two 600 MW units have been operating since 2015-16, supplying power to around 40 lakh households.

Decision Breakdown

The Supreme Court declined to shut the plant, holding that closing units that have run for years in a power-deficit State and serve 40 lakh households would harm the larger public interest. However, it made continued operation strictly conditional: the company must comply with every condition of the original EC and of the 2012 corrigendum, and must fully comply within the timelines it itself proposed for the conditions that were only partly met (the latest compliance report showed substantial compliance and no fundamental breaches, and the company had spent about Rs. 775 crore on the FGD system). The Court deliberately left open the larger legal question of whether a full cumulative impact assessment is compulsory for projects like this, to be decided in a future case. On the procedural question, it held that an aggrieved person can appeal to the NGT against a corrigendum to an EC, but where the original EC is not under challenge (or has already been upheld), that appeal is confined to the additional conditions only. The Court directed that this order is not to be cited as a precedent.

Lesson Learnt

Once a large project is up and running, courts weigh the public cost of shutting it down heavily, but they will make continued operation conditional on strict, time-bound environmental compliance. Communities affected by a project retain the right to challenge later modifications to an environmental clearance, but only on the new conditions if the original clearance has already been settled.

Environmental LawDelhi High Court

Pradeep Kumar Gupta vs. Delhi Development Authority

The Division Bench dismissed the appeal. It held that unauthorised parking itself is a misuse of the regulated floodplain, regardless of whether any dumping occurred. The Rs 5,000 compensation under the NGT's para 94(vi)(d) relates to throwing pooja or other material into the river, not to parking, so it did not apply. The lack of parking space due to renovation did not justify parking in a prohibited, environmentally sensitive area. The appellant had been given a personal hearing on its representation before the rejection order, so the no-hearing complaint also failed.

Decided 1 Oct 2026Read case
Environmental LawDelhi High Court

M/s Carnival Greens vs. Delhi Pollution Control Committee & Ors.

This was a very short, procedural order. The DPCC's counsel confirmed to the Court, on instructions, that only a show-cause notice had been issued so far and that the petitioner would be given a personal hearing before the DPCC decided anything. On the strength of this assurance being placed on record, the Court disposed of the writ petition without deciding any of the substantive issues raised (about infrastructure gaps or a provisional consent), since the DPCC had committed to hearing the petitioner out first.

Decided 18 Sept 2026Read case
Environmental LawDelhi High Court

M/S Ambria Cafe vs. Delhi Pollution Control Committee (DPCC) & Ors.

Notice was issued in the petition, and counsel for DPCC accepted notice on its behalf. DPCC's counsel clarified, on instructions, that only a show cause notice (not a final closure/compensation order) had been issued, and assured the Court that the petitioner would be given a personal hearing before any final decision was taken. Taking this statement on record, the Court disposed of the writ petition without deciding the underlying merits.

Decided 18 Sept 2026Read case
Environmental LawSupreme Court of India

M/S Punahchakran Private Limited v. Indotech Waste Solution

The Supreme Court held that the CPCB's 2016 revised guidelines for bio-medical waste facilities are mandatory and binding even though never published in the Official Gazette, since publication on the CPCB's official website was a reasonably sufficient mode of notice for such technical guidelines. However, the Court found that Punahchakran's relaxation from the standard 1-acre land requirement was validly granted: its facility was in a rural area (a permitted ground for relaxation) and the CPCB had been properly consulted and had imposed additional safeguard conditions. The Court also clarified that land allotment is not a strict legal precondition for starting the environmental-clearance application process, and that the original 2021 Terms of Reference remained valid (having a four-year validity period) even though the first EC based on it was earlier quashed, so the second EC could validly rely on that same original study. Concluding that the NGT had erred in quashing the second EC and CTE, the Supreme Court set aside the NGT's judgment and restored Punahchakran's approvals.

Decided 7 Sept 2026Read case
Environmental LawSupreme Court of India

Fisherman Care v. Government of India, Department of Animal Husbandry, Dairying and Fisheries

The Supreme Court held there is no real conflict between the Centre's power to regulate fishing in the EEZ (under Entry 57 of List I, exercised via the new EEZ Rules, 2025) and the State's power to regulate fishing within its territorial waters (under Entry 21 of List II, via the Tamil Nadu Marine Fishing Regulation Rules): these are two co-equal, autonomous legislative spheres that must operate together through "cooperative federalism." Following the Expert Committee's recommendations (that an outright ban on purse seine nets isn't justified but effective regulation is needed), the Union had already notified the EEZ Rules, 2025 creating an "Access Pass" system for vessels to transit through State waters into the EEZ. However, the Court found the on-ground implementation deeply flawed: of 257 access-pass applications, 226 were stuck pending verification by Tamil Nadu authorities, with only 6 passes actually issued, the lowest among all coastal States, which the Court said effectively amounted to an unwritten, unlawful ban. The Court directed Tamil Nadu to process applications efficiently and to frame rules designating a specific transit channel through its territorial waters for vessels headed to the EEZ, and disposed of the application on this basis.

Decided 2 Sept 2026Read case
Environmental LawSupreme Court of India

In Re: 2 Million Lives at Risk, Contamination in Jojari River, Rajasthan

Reviewing the SIT's report and the State's compliance report, the Court found continuing systemic failures, including that the State's report was silent on any action taken against responsible Rajasthan State Pollution Control Board officers, and issued a fresh set of detailed directions. These included: a scientific determination and demarcation of the High Flood Line and ecological buffer for the river system before any further industrial development (specifically flagging the proposed RIICO Industrial Area, Kakani, and the Ambey Valley Industrial Park as built too close to the river); an inquiry by the Chief Secretary into irregularities in land-use conversion and plot allotments at Ambey Valley; a comprehensive groundwater management strategy with a ban on new water-intensive industries in over-exploited "dark zones"; expedited transfer of identified lands to the Forest Department for ecological restoration; and a survey-and-removal drive against encroachments and illegal mining on riverbeds and floodplains. The Court also directed that action taken against RSPCB officers be reported within three days and listed the matter for further hearing on 22 September 2026, while noting that industrial pollution issues in Jaipur would be taken up separately once the present remedial framework is substantially implemented.

Decided 7 Aug 2026Read case