M/S. Interstate Construction v. National Projects Construction Corporation Ltd.

Civil Appeal · 2025 INSC 699Decided 15 May 2025
Civil Appeal No. 3461 of 2025
Justice Abhay S. Oka · Justice Ujjal Bhuyan

Background

Interstate Construction completed foundation work for National Projects Construction Corporation (NPCC) at the Ramagundam Super Thermal Power Project back in 1987, but disputes over withheld payments dragged on for decades, including multiple changes of arbitrator, before a final award was passed in 2020 by a retired High Court judge acting as sole arbitrator. The award granted interest in stages: an 18% pre-reference rate, a pendente lite rate compounding on the principal-plus-past-interest, and an 18% future-interest rate on the whole accumulated sum. NPCC challenged only the interest portion, and the Delhi High Court's Division Bench set aside those interest directions, holding the tribunal had wrongly awarded compound interest and improperly split the interest period. Interstate Construction appealed to the Supreme Court.

Decision Breakdown

The Supreme Court held that Section 31(7)(a) of the Act gives an arbitral tribunal discretion to award interest for the whole or any part of the period from the cause of action to the award, meaning it can validly split that period into sub-periods with different rates, as the arbitrator had done here. The High Court was wrong to say the statute permits only a single undivided period. On the compound-interest question, the Court traced the case law (S.L. Arora, later overruled by the three-judge bench in Hyder Consulting, followed in UHL Power and S.A. Builders) to hold that the "sum" on which post-award interest is calculated under Section 31(7)(b) legitimately includes the principal plus any interest already awarded up to that point, so charging further interest on that combined sum is not unlawful "interest on interest," it is simply how the statutory formula works. The High Court's order was set aside and the original arbitral award on interest restored.

Lesson Learnt

In arbitration, once a tribunal awards interest up to the date of the award, that combined amount (principal plus accrued interest) becomes the base on which further interest runs until actual payment: this is standard practice under Indian arbitration law, not an unlawful "compounding" of interest, and an arbitrator may also legitimately apply different interest rates to different phases of a long-running dispute.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case