M/S Jindal Steel and Power Ltd. v. M/S Bansal Infra Projects Pvt. Ltd.

Civil Appeal · 2025 INSC 640Decided 7 May 2025
Civil Appeal No. 6413 of 2025 (arising out of SLP (Civil) No. 21916 of 2024)
Justice J.B. Pardiwala · Justice R. Mahadevan

Background

Jindal Steel and Power had engaged Bansal Infra Projects to build 400 flats at its Jindal Nagar project, giving an advance secured by a bank guarantee. After repeated deadline extensions and alleged quality/performance failures, Jindal terminated the work and moved to encash the bank guarantee for unadjusted advances. Bansal filed a Section 9 arbitration petition seeking to stop the encashment; the Commercial Court refused to grant an immediate ex parte injunction and instead ordered notice to the other side. Bansal then went to the Orissa High Court under Article 227 of the Constitution (rather than appealing under the Arbitration Act), and the High Court granted interim protection against encashment, which Jindal challenged before the Supreme Court, raising several technical questions about which route of challenge was proper.

Decision Breakdown

The Supreme Court noted that the parties disputed whether an order rejecting an ex parte ad interim injunction under Order XXXIX Rule 3 CPC (issued alongside a Section 9 arbitration petition) is itself appealable under Section 37 of the Arbitration Act, or whether Article 227 was the only available route. Rather than deciding these disputed legal questions, the Court found that practical developments had overtaken the dispute: the underlying Section 9 petition was already substantially argued before the Commercial Court, an Arbitral Tribunal had since been constituted, and Bansal had repeatedly extended the bank guarantee's validity (through to 30 June 2025) so Jindal suffered no real prejudice from keeping the guarantee alive pending the Section 9 outcome. The Court therefore left the larger legal questions open, directed the Commercial Court to decide the Section 9 petition within eight weeks, and ordered the bank guarantee kept alive until then.

Lesson Learnt

Courts are generally reluctant to interfere with an unconditional bank guarantee except in cases of clear fraud or irretrievable injury, but where the guarantee has been kept extended and renewed without real harm to either side, the Supreme Court may simply let the underlying dispute proceed to a prompt decision rather than resolving every procedural or jurisdictional technicality along the way.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case