M/s. Kailash Nath Associates v. Delhi Development Authority & Anr.

Civil Appeal · Neutral citation not assigned (Civil Appeal No. 193 of 2015)Decided 9 Jan 2015
Civil Appeal No. 193 of 2015
Justice Ranjan Gogoi · Justice Rohinton Fali Nariman

Background

The appellant won a public auction for a Delhi plot at Rs.3.12 crore and paid 25% as earnest money, but could not pay the remaining 75% on time due to an industry-wide recession. The Delhi Development Authority (DDA) itself repeatedly extended the payment deadline over several years through two High-Powered Committees, and in 1987 offered to accept the balance with 18% interest: an offer the appellant accepted the same day. Years later, with no further notice to the appellant, the DDA cancelled the allotment and forfeited the entire Rs.78 lakh earnest money, then re-auctioned the same plot for Rs.11.78 crore (nearly four times the original price).

Decision Breakdown

The Supreme Court held that since the DDA itself had repeatedly extended the payment deadline and never put the appellant on fresh notice of a final deadline before cancelling the allotment, there was no breach of contract by the appellant in the first place, so forfeiture under the auction's own terms was not justified. The Court also laid down a detailed framework on Section 74 of the Contract Act, holding that forfeiture of earnest money is itself a form of "compensation for breach" and is lawful only where actual loss or damage is shown (or is a genuine pre-estimate of loss), and since the DDA ultimately profited enormously by re-selling the plot, it had suffered no loss at all, making retention of the earnest money arbitrary and impermissible, particularly since the DDA, as a State authority, is bound by Article 14 to act fairly and reasonably even in contractual matters.

Lesson Learnt

A government authority cannot simply pocket forfeited earnest money as a windfall: compensation for breach of contract under Indian law requires either proof of actual loss or a genuine pre-estimate of loss, and a public body must act fairly and give proper notice before treating a long-running, mutually-extended deal as "breached."

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case