M/s. Lancor Holdings Limited vs. Prem Kumar Menon and Others

Not available · 2025 INSC 1277Decided 31 Oct 2025
Not available
Justice Sanjay Kumar · Justice Satish Chandra Sharma

Background

Lancor Holdings (a builder) and Prem Kumar Menon and others (landowners) entered into a Joint Development Agreement (JDA) for construction of a building, with the parties to share the built-up area. Disputes arose and the matter went to arbitration. The Arbitrator reserved the award on 28.07.2012 but delivered it only on 16.03.2016, nearly three years and eight months later, without any explanation for the delay, and without finally resolving key issues, leaving the parties in an unworkable position where they would have to start fresh proceedings.

Decision Breakdown

The Supreme Court held that mere delay in pronouncing an arbitral award is not, by itself, sufficient to set the award aside; delay only vitiates an award where it demonstrably and adversely affected the arbitrator's findings. However, the Court found that this particular award was "unworkable" because it altered the parties' factual positions irrevocably (by allowing possession/construction to proceed) while leaving core disputes (relief on certain issues) unresolved, requiring fresh arbitration after 16 years, which the Court called a "travesty of justice." Rather than setting the award aside and sending parties back to square one, the Court invoked its extraordinary power under Article 142 of the Constitution to fashion a final, practical resolution itself: it validated the builder's earlier (technically unlawful) sale deeds, ordered forfeiture of the builder's ₹6.82 crore security deposit as a penalty, and directed payment of a further ₹3.18 crore to the landowners (totalling ₹10 crore), after which the builder could take possession of its share.

Lesson Learnt

Undue, unexplained delay by an arbitrator in delivering an award is a serious red flag, but courts will look at whether the delay actually damaged the substance of the decision, not just the calendar. Where undoing an award would trap parties in endless further litigation, the Supreme Court may use its special constitutional power to impose a complete, practical resolution instead of restarting the process from scratch.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case