M/S. Mitra Guha Builders (India) Company v. Oil and Natural Gas Corporation Limited

Civil Appeal · 2019 INSC 1225Decided 8 Nov 2019
Civil Appeal No. 5511 of 2012
Justice R. Banumathi · Justice A.S. Bopanna · Justice Hrishikesh Roy

Background

Mitra Guha Builders had two construction contracts with ONGC, each delayed well beyond the agreed completion date. The contractor invoked arbitration seeking payment of its final bills and other claims, while ONGC sought to recover liquidated damages for the delay under Clause 2 of the contract, which made the Superintending Engineer's decision on such compensation "final." The arbitrator disallowed ONGC's liquidated damages as a disguised penalty and the Single Judge of the Delhi High Court upheld this, but the Division Bench reversed, holding that liquidated damages under Clause 2 were an "excepted matter" outside the arbitrator's jurisdiction. The contractor then appealed to the Supreme Court.

Decision Breakdown

The Supreme Court held that Clause 2 of the contract was a complete, self-contained mechanism under which the Superintending Engineer alone could determine and levy compensation for delay, and the clause expressly made that decision final, meaning it was excluded from arbitration under the separate arbitration clause (Clause 25). Relying on its own earlier precedent in Vishwanath Sood v. Union of India, which dealt with an identically worded clause, the Court held that such "excepted matters," where the contract itself names a specific adjudicator and gives finality to that decision, cannot be reopened before an arbitrator. It distinguished a line of cases (like the BSNL v. Motorola case) where the clause only provided for quantifying damages without separately deciding fault for the delay. The Court therefore upheld the Division Bench's ruling that the arbitrator had exceeded his jurisdiction by disallowing ONGC's liquidated damages, and dismissed the contractor's appeals, directing settlement of the deposited amounts accordingly.

Lesson Learnt

When a government contract names a specific official (such as a Superintending Engineer) to decide a particular issue and declares that decision final, that issue becomes an "excepted matter" outside the arbitrator's jurisdiction: parties cannot later route such disputes through arbitration no matter how unfair the outcome may seem.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case